Press enter to search, esc to close
Welcome to the spring edition of our contract law update series. In this update, we provide a round-up of some of the most significant contract law cases in the first few months of 2025 to help our clients stay up to date, when drafting and negotiating contracts.
Date published
20 May 2025
EE Ltd v Virgin Mobile Telecoms Ltd [2025]
The Court of Appeal upheld a decision to strike out a claim for lost charges arising from an alleged breach of an exclusivity clause in a supply agreement. It ruled that the claim was effectively for “anticipated profits” and the exclusion clause therefore applied.
The case highlights the importance of drafting excluding clauses carefully to accurately allocate contractual risk. The diverging views of the Court of Appeal judges show that there is no uniform interpretation of phases such as “loss of profits” or “anticipated profits”; instead, the meaning will depend on the specific wording of the contract and the wider factual matrix.
Virgin Mobile Telecoms Limited (VM) and EE Limited (EE) entered into a Telecommunications Supply Agreement (TSA) in 2013. Under the TSA, VM agreed to use EE’s mobile network infrastructure to provide its customers with 2G, 3G and 4G mobile services. The TSA included a provision whereby VM agreed to use the EE network exclusively for the provision of those services to its customers.
VM subsequently entered into an agreement with Vodafone for the supply of 5G services and began migrating customers from the EE network to the Vodafone network. EE insisted this was a breach of the exclusivity clause and consequently brought a claim against VM for the loss of revenue incurred as a result of the customers having migrated to a different network.
VM denied a breach had occurred and argued that, in any case, EE was contractually prevented from bringing a claim due to the exclusion of liability for loss of “anticipated profits” set out in clause 34.5(a) of the TSA: “…Neither party shall have liability to the other in respect of: (a) anticipated profits”.
The High Court granted summary judgment for VM, holding that VM’s liability for any alleged diversion of customers to alternative networks was captured by the exclusion in clause 34.5, which meant EE could not succeed in their claim. EE decided to appeal on the following grounds:
Although Phillips LJ was swayed by EE’s arguments, the majority of the Court of Appeal ultimately ruled in favour of VM.
The key issue was whether it was correct to characterise the claim as a claim for loss of profits which was subject to the exclusion clause. In the leading judgment, Zacaroli LJ stated that “there is no overarching principle of law that limits an exclusion of liability for loss of anticipated profits to losses other than expectation loss or diminution in price”. In this case, the view was that in the relevant clause "anticipated profits" was used interchangeably with "loss of profits". As such the claim was caught by the exclusion clause.
The caselaw advanced by EE failed to provide any assistance. The facts in EE’s authorities were different to the present case and none of them were persuasive in determining that an exclusion covering “loss of profits” could not cover a claim for “diminution in price”. If the parties had intended clause 34.5(a) to cover only direct loss of profit claims that do not fall within the ambit of expectation loss, they could have done so specifically.
The judgment also dismissed EE’s argument about the commercial viability of the contract. Although damages and injunctive relief would have been difficult options for EE in the present case, this did not render the contract a “commercial absurdity” because there existed a range of circumstances where remedies could have been sought in the event of a breach. The judgment also noted that the clause was part of a lengthy contract drafted with the assistance of legal advice on both sides, involving a careful allocation of risk for both parties.
Dissenting, Phillips LJ considered that if EE had intended to give up the right to anticipated profits in these circumstances, then clearer language to that effect could have been used.
Disclosure and Barring Service v Tata Consultancy Services Ltd [2025]
The Court of Appeal upheld Constable J’s ruling that the customer was not entitled to compensation for delay, as the customer had failed to comply with the associated condition precedent.
This case details the criteria for determining if a clause is a condition precedent and emphasises the need for clear drafting in such clauses.
The matter concerned a digital transformation project, as well as ‘business as usual’ services, between Tata Consultancy Services Ltd (TCS) and Disclosure and Barring Services (DBS).
TCS claimed more than £100m in damages for delays in connection with mismanagement of a third-party IT hosting provider, and a failure to communicate decisions, by DBS. DBS made a counterclaim for delays due to the software not being ready for installation, and for issues with the quality of the software.
Each party argued that to recover either damages or compensation for delays, the claimant party had to comply with certain conditions precedent under the contract.
Constable J found in favour of TCS, and the decision was subsequently appealed by DBS to the Court of Appeal.
The Court of Appeal found that DBS was not entitled to delay payments as it had failed to take the required action in a clause that amounted to a condition precedent. It was upheld that DBS was required to complete a Non-Conformity Report (NCR) before exercising its right to delay payments, which it had failed to do.
The applicable Clause (Clause 6.1) stated “if a Deliverable does not satisfy the Acceptance Test Success Criteria and/or a Milestone is not Achieved due to [TCS’] Default, [DBS] shall promptly issue a non-conformance report to [TCS]…. [DBS] will then have the options set out in clause 6.2.”. Under Clause 6.2, one option available to DBS was to recover a delay payment from TCS. TCS argued that DBS’s entitlement to a delay payment was contingent on submission of an NCR in accordance with Clause 6.1.
The court agreed with this interpretation of Clause 6.1. DBS countered that only the first limb of the Clause applied (i.e., failure of an Acceptance Test or failure to meet a Milestone – not the completion of an NCR). The court found that the Clause was sufficiently clear that an NCR was a condition to seeking a delay payment. Coulson LJ stated that the use of the words “if” and “then” were enough to show the steps in Clause 6.1 were a condition for relying on Clause 6.2. Lewison LJ added that almost any clause that starts with "if" is conditional; he also noted that the Clause was split into two sentences, further clarifying that the first limb must be satisfied for the second limb to be effective.
The court noted the following points in its interpretation of the Clause:
CE Energy v Bashar & another [2025]
The High Court considered the meaning of section 49(2) of the Sale of Goods Act 1979 (SGA) as to the seller’s ability to claim for the price of goods where it is payable on a "day certain irrespective of delivery" even though title has not passed to the buyer.
This case also provides guidance on interpreting guarantees.
Ultimate Oil and Gas DMCC (UOG) contracted with CE Energy DMCC (CEE) under a series of spot contracts for the sale of gasoil and jet fuel. The terms of these contracts provided that CEE retained title in the goods until payment was made by UOG. UOG later failed to make payment in respect of outstanding sums due under these contracts, and the parties subsequently entered into a ‘Payment Agreement’, in which it was agreed that UOG would pay its debts in instalments, and that CEE would supply two further spot cargoes (the New Spot Cargo) if UOG complied with its obligations. The owner and chairman of UOG, Mr Bashar, also provided a personal guarantee in respect of UOG’s obligations under the Payment Agreement.
UOG paid its first instalment under the Payment Agreement, and accordingly CEE agreed to supply the New Spot Cargo. However, when UOG failed to make payment for the New Spot Cargo, and to comply with its remaining obligations under the Payment Agreement, CEE did not supply the additional cargo and issued a claim against UOG for the unpaid price of the goods, and a further claim against Mr Bashar under the personal guarantee. It also reactivated existing arbitral proceedings between the parties in respect of UOG’s outstanding debts to CEE.
Section 49(2) SGA 1979
Due to the presence of the retention of title clause, the court was required to consider whether the claim was within the scope of section 49(2) of the SGA, which provides that a seller may claim for the price of goods where it is payable on a "day certain irrespective of delivery", even where title has not passed to the buyer.
The relevant contract provided for delivery of the New Spot Cargo by offshore ship-to-ship transfer between vessels, with payment due latest 45 calendar days from the Notice of Readiness provided by the daughter ship in respect of its arrival at Lagos to offload its cargo. UOG argued that a “day certain irrespective of delivery” required the day to be defined in the contract, in a way which was neither logically nor practically connected to delivery.
The court disagreed. It held that a day was certain if it was ascertainable, including by reference to an uncertain event or something that one of the parties or a third party did, and considered that the phrase “irrespective of delivery” was to be interpreted as meaning "whether or not the date certain is fixed by reference to delivery". As such, the judge was satisfied that the provision of the Notice of Readiness was a “date certain” on the basis that, although not specified as a fixed date, it was ascertainable following the occurrence of an event specified in the contract. It considered this was “irrespective of delivery” because, although notice would likely occur following delivery, it would not be bound to coincide with delivery and the contract did not make payment conditional upon delivery having occurred.
The Guarantee
CEE argued that: (i) the guarantee provided by Mr Bashar was a demand guarantee, and as such Mr Bashar was under an obligation to pay any sum demanded by CEE in good faith, notwithstanding UOG’s actual liability, and (ii) in the alternative, that UOG and Mr Bashar were contractually estopped by the Payment Agreement from denying any liability to make payment of the outstanding sums. Mr Bashar contended that the guarantee was a surety guarantee, under which he would only be liable to perform following the liability of UOG being established through award or judgment.
The court concluded that this was a surety guarantee, and therefore CEE would be required to demonstrate UOG’s liability in respect of the outstanding sums guaranteed by Mr Bashar. It considered that it was able to do so, on the basis that the Payment Agreement contained “promises to pay specified proportions of outstanding sums at particular dates”, and “a succession of very precise and express admissions about what was due under the previous contracts”, which were described as “irrevocable”. As such, UOG, and by extension Mr Bashar, were contractually estopped from relying on those admissions. The Court held that Mr Bashar had guaranteed the underlying liability and confirmed that there was no requirement for CEE to first obtain a judgment or award against UOG in order to call upon the performance of the personal guarantee.
Durber v PPB Entertainment Ltd [2025]
The High Court considered unusual and onerous contractual provisions which had not been brought adequately to the attention of the claimant consumer and therefore, it was held they were not incorporated into the relevant contract, nor could they be relied upon.
This case reiterates the importance not only of the drafting of terms and conditions in consumer contracts, but also the presentation of such terms if they are to be enforceable against consumers.
In October 2020, Mrs Durber played ‘The Wild Hatter’ game on Paddy Power’s website, a two part game involving a fruit machine and a wheel of fortune (Game). Mrs Durber was informed that she had won a jackpot prize and was asked to spin the wheel of fortune. On the second part of the Game, Mrs Durber was shown that she had won the ‘Monster Jackpot’ amounting to nearly £1.1million but was only paid the ‘Daily Jackpot’ amounting to £20,265.14 (a significantly less sum).
Paddy Power argued that although Mrs Durber’s device showed her as winning the ‘Monster Jackpot’, there had been a mapping error in the Game’s animations whereby the wrong jackpot outcome had been displayed on Mrs Durber’s device.
Paddy Power sought to rely on contract terms stating its server records (determined by random number generator software) were definitive over Mrs Durber’s screen display and a separate exclusion clause for errors.
The pertinent clauses Paddy Power relied upon were as follows:
“You fully accept and agree that random number generator ("RNG") software will determine all outcomes of Games on the Games Website. In the event of a discrepancy between the results displayed on your computer and a Game's records on our server, our records shall be regarded as definitive.”
(referred to as “clause B1”); and
“In the event of systems or communications errors relating to the generation of any result, bet settlement or any other element of a Game, we will not be liable to you as a result of any such errors and we reserve the right to void all related bets and plays on the Game in question."
(referred to as “clause B2”).
Mrs Durber argued that the rules of the Game (Game Rules) which said winnings would be determined by what was on screen (in contrast to clause B1 which stipulated that Paddy Power’s server records were definitive in determining winnings) should take precedence over the wider terms. Mrs Durber further asserted that clause B1 and clause B2 were not incorporated into the contract because they were onerous, unusual and in any event were unfair under consumer law.
Finding in favour of Mrs Durber, Mr Justice Ritchie held:
HNW Lending Ltd v Lawrence [2025]
The High Court considered that section 1(1)(a) of the Contracts (Rights of Third Parties) Act 1999 was not limited to the enforcement by a third party of a term purporting to benefit the third party. In this case, it was sufficient that the contract expressly provided that the third party could enforce the term.
Although this case concerned the terms of a loan agreement, it potentially widens the scope of section 1(1) of the Contracts (Rights of Third Parties) Act 1999 in the context of other commercial contracts.
Ms Lawrence carried on business as a property investor with a portfolio of residential properties in London and Surrey. She entered into a Loan Agreement in 2018 with an unnamed lender acting by its security agent, HNW. The lender was identified in Schedule 4 by the number "1" and was described as " a person … who lends money through HNW Lending Limited who has granted permission for 'HNW Lending Limited to act as their Security Agent in entering into and administering this loan to the Borrower."
Clause 26.7 of the Loan Agreement stated:
“The Borrower and Lender agree that, while HNW Lending Limited is not a party to this Loan Agreement, HNW Lending Limited may take the benefit of and specifically enforce each express term of this Loan Agreement and any term implied under it pursuant to the Contracts (Rights of Third Parties) Act 1999.”
In 2021, HNW sent a demand to Ms Lawrence notifying her that the loan amount and interest were due and payable, and the security was enforceable. Ms Lawrence sought to strike out HNW’s claim on the basis that HNW had no standing to bring a claim because it had no enforceable rights under the charge and Loan Agreement. This argument was based on a county court judgment in August 2024, also involving HNW, which held that because the HNW was not expressed to benefit from the agreement, there was nothing it could enforce under the Contracts (Rights of Third Parties) Act 1999.
Reaching a different conclusion to the county court, the judge decided that HNW did have title to sue on the Loan Agreement and the charge, and the claim should not be struck out.
The judge considered that clause 26.7 must have been drafted with the 1999 Act in mind and with the intention of conferring on HNW equivalent rights to those of the lender, enabling HNW to enforce obligations owed to and benefitting the lender. He noted that there was a dearth of case law on the scope of section 1(1). The example given in Chitty on Contracts of a situation where a third party may enforce a term of the contract pursuant to section 1(1))(a) (" if the contract expressly provides that he may ") is materially different from what the parties appear to have had in mind in this case.
Contrary to what Chitty's example might suggest, the judge considered that section 1(1)(a) is not limited to the enforcement by a third party of a term purporting to benefit the third party, since this type of term is specifically addressed in section 1(1)(b). It is sufficient that the contract expressly provides that the third party may enforce the term (as clause 26.7 did in this case). Alternatively, clause 26.7 was effective pursuant to section 1(1)(b) to confer on HNW the benefit of the covenants and rights of enforcement owed to the lender.
The judge concluded that construing clause 26.7 as legally effective also accorded with the principle that the courts should endeavour, if possible, to give effect to the parties' contractual provisions rather than treating any part of them as “otiose”.
Contributors: Elizabeth Maloney, Giorgio Basile, Francesca Jack, Rebekah Lengyel and Laura Smurthwaite
If you would like to discuss any of the contract topics detailed in this update, or for more general commercial contract support please do get in touch with one of the below contacts.
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at May 2025. Specific advice should be sought for specific cases. For more information see our terms and conditions.
RELATED INSIGHTS AND EVENTS
View allRELATED SERVICES