Press enter to search, esc to close
Ofgem has published an open letter signalling further changes to TMO4+, the proposed new regime for transmission-related connections.
In addition to the connection criteria already proposed – relating to projects having land secured and having a date for submitting a planning application – there will be new criteria relating to “strategic need” for the project, including by reference to the project’s location and technology type.
In particular, the TMO4+ process will need to deliver a technology and location mix that is aligned with both the forthcoming 2023 Clean Power (“2030CP”) policy to be produced by the new Labour Government and the Strategic Spatial Energy Plan (“SSEP”) to be produced by the ESO (soon to become the “NESO”).
To allow for this, the timetable for implementing a revised TMO4+ has therefore been extended from January 2025 to “Q2 2025”. However, to achieve this will clearly depend on when 2030CP and the SSEP are available (and this is not currently clear). They will also need to be digested and reflected in new methodologies to be produced by the system operator, which is itself in a process of change from ESO to a publicly owned “NESO”.
Whilst the original design of a market-led generation sector in GB has been eroded over time by increasing interventions, particularly in relation to revenue support, this still represents a significant change towards more strategic, central planning.
There is also a risk that it derails the progress made on TMO4+ over the Summer, during which time some of the detail around the reforms was filled in, for example, in relation to the application windows, the Gate criteria and the knock-on effects on connecting to the distribution networks.
This note provides an update on the connection reforms, covering both the recent updates and the progress made on CUSC Modification Proposals 434 and 435 since the time of our initial Insight: NGESO signals plans to widen scope of connection process reform - TLT LLP of 1 May 2024.
In May 2023, Ofgem published its Open letter on future reform to electricity connections process which set out the various challenges the connections reform process faced and the actions that needed to be taken in the short to mid-term to ensure that GB is on track to meet its 2030 and 2050 clean energy targets.
In November 2023, Ofgem and the Department for Energy Security and Net Zero (“DESNZ”) then published the Connections Action Plan. This summarised Ofgem’s and the Government’s vision for a reformed connections process. The key agreed action which was to be taken forward to reduce grid connection timescales related to the creation of a new connections process that facilitates viable projects and is aligned with the future strategic build and spatial energy plan (i.e. the SSEP).
Since then, connections reform has moved at pace and the ESO, Ofgem and the industry have continued to progress key initiatives. In December 2023, ESO published its Final Recommendations Report which identified Target Model Option 4 (“TMO4+”) as the preferred route and ESO set out an Implementation Plan proposing 1 January 2025 as the ‘go-live’ date for TMO4+. (Please refer to our May 2024 Insight for additional background and context.)
Since then, work on both CMP434 and CMP435 (the code modification proposals to implement TMO4+ and wider grid connection reform) has accelerated with the ESO Workgroup convening sixteen times to discuss perceived issues, which ultimately resulted in ESO publishing the Workgroup Consultation Report for CMP434 and CMP435 on 25 July 2024 (the “July Reports”). These provide further detail on a number of aspects of TMO4+.
The key elements outlined in the July Reports relate to:
Three high-level concepts are proposed which are:
These concepts will be lightly codified within the CUSC, with the detail of each methodology to sit outside code governance and instead be prepared by the ESO and approved by Ofgem. At present, there is still very little detail on what each of these methodologies will comprise, but the ESO plans to consult on these in November 2024.
The Primary Process relates to the introduction of the “annual application window” and the gated approach to connections under TMO4+, being Gate 1 and Gate 2. It is envisaged that under the Project Designation Methodology, there will be exceptions to this Primary Process. Such exceptions will relate to projects which are designated to be critical to the security of supply or materially reduce network constraints.
Whilst not in either Report, the ESO has indicated that Gate 1 will be optional for some projects, so that “project ready” projects can 'skip' Gate 1 and go straight to Gate 2.
In our May 2024 Insight, we reported that there would be a gated approach with criteria which must be achieved to ensure that a project is “project ready” and can proceed to “Gate 2” and a firm connection. The July Reports confirm the criteria from May relating to securing land rights and a commitment to a date for submission of an application for planning consent.
In relation to land, developers will need to have secured rights to lease or own the land (and it is made clear that an exclusivity agreement is not sufficient to meet the Gate 2 criteria).
However, in addition, the process is moving towards a “strategic need” approach rather than a “project ready” approach, described below.
As previously reported in our May 2024 Insight, ESO has confirmed that TMO4+ will be retrospective in nature and the details of this are set out in the CMP435 July Report: when TMO4+ is implemented, all existing contracted projects in the queue will have their connection agreements converted to either a Gate 1 or a Gate 2 agreement, depending on whether they have met the Gate 2 criteria at the Implementation Date.
This will be of particular interest to projects in the current transitional arrangements (with “Step 1” and “Step 2” offers) which have been given a firm date in their Step 2 offer, but may not have achieved the TMO4+ Gate 2 criteria when these are implemented and will therefore lose their place in the queue.
In our May 2024 Insight, we noted that the impact of TMO4+ on small- to medium-sized projects was yet to be clarified. In the July Reports, this element has been given some clarification and there is a separate process for small and medium embedded (i.e. distribution connected) power station projects. For such projects, the ESO proposes to introduce the concept of a Distributed Forecasted Transmission Capacity (“DFTC”) submission. In essence, a DFTC submission will involve the DNO, or where applicable an IDNO, submitting a DFTC to the ESO during the Gate 1 “annual application window”.
The aim is that this will be a view of forecasted capacity volume of connections that may be made in the future, and it is anticipated that such submissions will allow the ESO and the relevant Transmission Operators to forecast the anticipated transmission capacity required for these embedded projects.
This will largely follow current practice with DNOs using the existing Project Progression/Transmission Impact Assessment process to submit Gate 2 applications on behalf of embedded customers.
Since the publication of the July Reports, Ofgem has proposed that the connection reforms being proposed should go “further and faster” and that ESO should align the reforms process to 2030CP and the SSEP. This prompted a letter from the ESO on 9 September 2024 requesting a delay to the Implementation Date of TMO4+ and in turn the open letter from Ofgem of 16 September 2024 “on achieving an accelerated alignment on the connection reforms process and the strategic plan”.
The purpose of ESO’s letter to Ofgem was to request an urgent extension to the timetable for the implementation of CMP434 and CMP435.
ESO’s rationale for the need to extend the timeline is due to the “unprecedented scale and ambition” of the new connection reforms being put forward as a result of aligning the currently proposed reforms with 2030CP and the SSEP. ESO also note that as the key methodologies (referred to above) will not be in place until Q1 2025 it is necessary to delay the Implementation Date.
As a result of this delay and the time required to develop the key methodologies, ESO sought an extension to the Implementation Date to a date in Q2 2025 (however, no further information is provided as to when exactly in Q2 2025 this will be). Ofgem has indicated that it has no concerns with pushing the date back to Q2 2025.
For a detailed overview of the new connections timeline, please see the table outlined in the ESO letter here.
Ofgem’s open letter on the reformed regulatory framework on connections provides an update on the processes it has undertaken to progress key initiatives since the Connections Action Plan.
Ofgem is of the view that due to the accelerated targets brought in by the new Labour Government this requires the current regulatory changes to go further than the TMO4+ code modification proposals and faster.
It was initially planned (if not explicitly stated) that the connections reform would be carried out in two phases. However, because of the accelerated targets, Ofgem is of the opinion that this represents an opportunity for the current reforms to be aligned with the strategic planning demands of the GB energy system (which are to be set out in the 2030CP and the SSEP).
A potential reason for the faster approach is due to current analysis showing that while the current proposals would likely reduce the size of the queue significantly, there is a risk that such reduction will not deliver a technology mix which aligns with the goal of creating a secure clean energy system by 2030.
Therefore, it appears that there will be technical or technology requirements built into TMO4+. We understand that Ofgem and ESO are looking into setting capacity caps based on size and/or a locational requirement, across different technologies, with such restrictions being outlined in the SSEP.
This approach confirms a suspicion that the sector has long had that the process would not remain technology-agnostic, and Ofgem and ESO were planning on applying technology- and location-specific Gate 2 criteria under TMO4+ (albeit with relevant carve-outs to the criteria for strategic projects). It looks very much like Ofgem is now opening the door to including “strategic need” in its connection criteria, which prefers certain technologies in certain geographic areas over the simple “project ready” approach put forward for several months.
Ofgem also calls for the National Energy System Operator (NESO) to be at the forefront of this change given it is taking on new and enhanced responsibilities (which include the coordinated development of the whole energy system). Thus, through its licence, NESO will take greater control over the connections process for those applications connecting to, using or impacting the transmission system. To ensure that the interests of the industry are safeguarded, and NESO meets its statutory objectives, such control should be done in a form that facilitates the delivery of the strategic plans in an open, transparent way (within the parameters of the new governance framework that will be set out by Ofgem following a consultation).
To implement this “further and faster” approach and to ensure NESO can control the connections process, additional necessary licence modifications are now proposed. In the open letter, Ofgem makes it clear that it does intend to consult on the new licence modifications to enable the implementation of a TMO4+ connections process and the three (non-codified) methodologies (referred to above).
Whilst it was always expected, if not explicitly stated by Ofgem, that over time the Gate 2 criteria would evolve to accommodate a move towards a more centrally planned system, Ofgem’s letter signals that this will happen much sooner than expected, with Gate 2 criteria now intended to reflect such “strategic need” from the Implementation Date.
This creates further uncertainty for projects, including those currently in the system, over whether they will meet any new “technology” criteria.
For example, there will be projects with an existing connection agreement who are on track to meet the “land and planning” Gate 2 criteria originally proposed, and were therefore expecting to maintain their existing, firm connection date, which do not now know what the eventual “technology” criteria will be for their location and therefore whether they will meet them or instead be downgraded to a Gate 1 indicative offer. In addition to the three methodologies outlined above, there may also need to be a methodology for deciding between projects to address the issues that arise from the above.
As a result, developers will be anxiously awaiting publication of both 2030CP and the SSEP to consider how their project’s technology and location will fit in.
As noted above, the plan is for key aspects of the connection reforms and new rules to sit outside the CUSC and its current code governance, meaning that the three proposed methodologies for determining winners and losers will lack a layer of protection that is currently in place, as these documents can be changed more quickly and easily than the CUSC itself and without the potential of an appeal to the CMA.
On the other hand, from a practical perspective, we recognise that the methodologies will need to be living documents that can be updated in real time to accommodate projects as they come forward and are built.
This does represent a further step away from a market-led sector towards a more centrally planned electricity market. On the other hand, the private sector is likely to welcome any insight as to where it should locate projects if that results in better utilisation of those projects.
Another key question here is whether this new extended timetable for TMO4+ is realistic. Given the development of the three methodologies is dependent on the publication of the SSEP and the 2030CP and given the complexity of the reforms being sought, there seems to be potential for further delays to the process to follow.
Linked to the above, what happens in the meantime? As of 2 September 2024, ESO says that all new connections will receive “stage 1 offers” under the new transitional arrangements. Will projects continue to apply for indicative connection offers and seek to meet the published Gate 2 criteria at the relevant time, without knowing whether they will meet the eventual “technology” aspects of the criteria?
This may have a temporary chilling effect on new applications while developers wait and see.
Before the ESO and Ofgem proposals can come into effect, the current code modification processes will have to be completed. Even if the TMO4+ methodologies and the “strategic need” approach end up sitting outside code governance, industry input will still be crucial to inform the finalisation of the relevant criteria. In addition, there will also be a need for amendments to the CUSC and the licence conditions to ensure that the new reforms are given life.
Whilst we now know that there will be potentially technology-based Gate 2 criteria and the door has been opened to a strategic planning approach that prefers certain technologies in certain geographic areas, there are still key questions relating to what technology and locations this should apply to and what carve-outs to the criteria are anticipated.
There is still a great deal of uncertainty as to what shape the methodologies and the technology and location mix will take going forward, given these will not and cannot be developed until after the 2030CP and SSEP are published.
It will also be interesting to see how the NESO meets the challenge of this new strategic role, given its decisions will inevitably create winners and losers. There will not be much scope for bedding in following its forthcoming designation on 1 October.
If you are currently in the grid connection queue and have any queries about any of the points raised in this article and how they may impact your project, please feel free to reach out to our team (details below) to find out how we can assist you with preparing for the new TMO4+ and the “strategic need” approach.
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at September 2024. Specific advice should be sought for specific cases. For more information see our terms and conditions.
Date published
20 September 2024
RELATED INSIGHTS AND EVENTS
View allRELATED SERVICES