
Beyond the Building Safety Act: fire safety remediation works outside the statutory regime
Essendi UK Hotels 2 Limited v London Property Company Limited
The recent decision of the Technology and Construction Court (TCC) in Essendi v LPC is an important reminder that liability for building safety is not confined to the Building Safety Act regime. As the case concerned a hotel, it fell outside the remit of the Building Safety Act – nevertheless, the court found that, under the terms of the parties’ lease, the landlord was required to remove and replace dangerous ACM cladding.
Background
In this case, the TCC considered who was responsible for removing dangerous cladding on a hotel building: the landlord or tenant?
The case concerned a multi-storey tower block which housed the Ibis London Wembley Hotel. Essendi UK Hotels 2 Limited (Essendi) was the original owner of the freehold of the hotel building. In 2005 Essendi installed replacement cladding on the building. The cladding panels were made of Aluminium Composite Material (ACM), which is comprised of a highly combustible polyethylene (PE) core sandwiched in between outer aluminium sheets.
In June 2007 Essendi sold the hotel building to WHL and immediately leased it back. Under the terms of this Original Lease, Essendi retained an obligation to remedy defects in the cladding panels, up to a Cut Off Date in May 2017. Coincidentally, this Cut Off Date fell one month before the Grenfell fire (June 2017).
London Property Company Ltd (LPC) acquired the freehold of the property in 2018 and, in March 2019, granted a new lease to Essendi. This new lease (referred to in the judgment as the Current Lease), was issued almost 2 years after the Cut Off Date in the original lease, and it did not place any obligations on Essendi to remedy defects in the cladding.
By 2024 investigations had confirmed that the cladding panels presented a fire risk to the hotel. The hotel closed in July 2025.
The principal issue before the TCC was who, if anyone, was responsible for undertaking the major building safety works to remove the external cladding panels from the hotel building: LPC or Essendi?
Essendi's arguments
Essendi's case was that LPC, as landlord and owner of the hotel building, was responsible for removing the cladding panels because:
- As landlord, LPC were under an obligation to keep the premises in "good condition". As long as the cladding panels remained on the hotel building, the premises were not in a "good condition", due to the fire-safety risk they presented; and/or
- The Current Lease required LPC to comply with all "legal obligations" that the law imposed on it. Under the Regulatory Reform (Fire Safety) Order 2005 (FSO), LPC was required to ensure that the hotel building was safe from fire risks. Essendi argued that LPC's refusal to remove the ACM cladding panels amounted to a breach of the FSO and therefore, the Current Lease; and/or
- As a result of the fire risks caused by the cladding, on the advice of fire safety experts, Essendi had closed the hotel. Essendi therefore argued that LPC's refusal to remove the cladding panels deprived Essendi of using the premises for the purpose for which the Current Lease had been granted (i.e. operating a hotel).
The TCC's decision
A: Yes.
The court concluded that LPC had a strict liability obligation to keep the premises in “good condition”. As such, the court held that it was irrelevant that LPC did not know, in March 2019, that cladding panels had an ACM PE core. LPC was still responsible for removing and replacing them.
The covenant to keep a premises in “good condition” is wider than an obligation simply to repair. It extends to requiring a landlord to put a building into a satisfactory condition, as judged by the standard of a hypothetical tenant who is reasonably minded. That is the case even if the premises were not in this condition previously.
The TCC held that an obligation to keep the premises in "good condition" included a requirement to remove and replace cladding, or remedy other inherent defects which (a) created a significant fire safety risk, and (b) required remediation to make the building safe for occupation and to comply with the FSO.
LPC's refusal to remove and replace the cladding panels therefore amounted to a breach of the Current Lease.
A: Yes.
As the "responsible person" under the FSO, LPC was required to undertake fire risk assessments and maintain fire precautions as may reasonably be required to ensure that the building was safe for persons on the premises or in its immediate vicinity.
The TCC held that removing the cladding panels was necessary to ensure safety from fire. LPC's failure to do so therefore amounted to a breach of the FSO and therefore, the Current Lease.
A: No.
The TCC held that Essendi had acted reasonably in closing the hotel due to the fire safety risk, but there was no basis to imply an obligation on LPC to ensure that a hotel could be operated from the building which it leased to Essendi.
LPC's Case
LPC argued that Essendi, who installed the cladding panels in 2005, had been under an obligation under the Original Lease with WHL to remedy any defects in the cladding panels until the May 2017 Cut-Off Date. Therefore, LPC contended, Essendi ought to have replaced the cladding panels prior to the Cut Off Date, and their failure to do so constituted a breach of that obligation.
However, the TCC held that before Grenfell (June 2017) the construction industry did not fully appreciate the fire safety risks associated with ACM PE core cladding panels. Accordingly, the TCC held that for LPC to argue that Essendi had been responsible for replacing the cladding panels prior to the Cut-Off Date (May 2017), it had to establish that Essendi either:
- had been under an obligation in the Original Lease to replace the cladding panels irrespective of whether Essendi knew or ought to have known that they were defective; or
- was, or ought to have been, on notice of the fire safety risk and the need to take measures to remedy this defect.
The TCC decided that LPC failed to establish either of these requirements. Though the cladding panels were considered "defective" because of the fire risk they presented, there was nothing to put Essendi on notice as to the fact that they were defective, or of the need to investigate as to whether they were defective, because:
- they had not deteriorated in a way as to make them more of a fire safety risk than they already were upon installation; and
- Essendi could not have been aware of the intolerable fire safety risk that the Cladding Panels posed prior to the Cut-Off Date and therefore could not have been under an obligation to remedy them. The Cut-Off Date was prior to the Grenfell fire and the resulting increase in awareness / knowledge of the dangers of ACM PE core cladding panels that followed.
Key Lessons from Essendi v LPC
Essendi provides an important reminder that liability for building safety is not confined to the Building Safety Act regime. Owners, landlords, tenants and investors should carefully review existing lease obligations, fire safety responsibilities and historic contractual arrangements, as liability for remediation may arise through conventional property and contractual principles even where statutory remediation orders are unavailable.
Key Lessons from the case:
- "Good condition" obligations extend beyond simple repairing obligations. As in this case, it may require a landlord to undertake substantial remediation work, such as removal of unsafe cladding.
- Breach of fire safety legislative duties may have contractual consequences. In this case, the landlord's obligations under the FSO were capable of giving rise to a breach of the lease, which required compliance with legal obligations.
- It is important to understand historic contractual arrangements, including sale and leaseback arrangements, repairing covenants and defect liability provisions, all of which may impact where responsibility lies for building safety remediation.
- Timing can be crucial. LPC's case that Essendi ought to have removed the cladding prior to the May 2017 Cut Off Date fell flat, largely due to the fact that the risks associated with ACM PE cladding panels only became widely known post Grenfell.
- Courts will order specific performance in suitable cases – including orders requiring landlords or building owners to carry out fire safety remediation, rather than simply awarding damages.
If you have any questions about building safety, or the subjects discussed in this article, please contact Dominic O'Tuminu, Katherine Doran or your usual contact at TLT.
Authors: Dominic O'Tuminu and Katherine Doran
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at July 2026. For more information see our terms & conditions.
Get in touch
Get in touch
Insights & events

Beyond the Building Safety Act: Fire safety remediation works outside the statutory regime

Infrastructure Planning Blog 59: A solar decision, revised National Policy Statement for Ports and other news

Infrastructure Planning Blog 58: Guidance, judgment and decision

Infrastructure Planning Blog 57: An environmental judgment and a consented solar farm

Contribution claims, vicarious liability, and Unfair Contract Terms Act: lessons from Sutton and East Surrey Water Plc v Monarch Chemicals and Muztrans Ltd

Infrastructure Planning Blog 55: Goodbye statutory consultation and other planning infrastructure news

Infrastructure Planning Blog 52: Changes to Habitats Regulations, application fees, a parliamentary petition, and a solar farm refusal

Infrastructure Planning Blog 51: A veritable fountain of infrastructure planning news

London Luton Airport expansion finally cleared for take-off?

Infrastructure Planning Blog 50: An offshore wind DCO, safeguarding transmission and the King’s Speech

Infrastructure Planning Blog 49: Sundowner and BNG on the up

Building Liability Orders: First fully contested judgment on BLOs delivers clarity

Infrastructure Planning Blog 48: Legal challenge ruled totally without merit, pollution control regimes and football stadiums

The UK Carbon Border Adjustment Mechanism and potential impacts on projects

Infrastructure Planning Blog 47: Overhead line changes, and enabling data centres

Infrastructure Planning Blog 46: BNG for NSIPs defined but delayed and other news

Impact of flexible working on towns and cities - the market and legal considerations

Nick Evans joins TLT as partner placing the firm at the helm of infrastructure, planning, public law and future energy in the UK

TLT expands future energy and infrastructure expertise with new Partner appointment

TLT strengthens public sector infrastructure and future energy offering with two new partners

TLT strengthens construction expertise with third partner hire in six months

TLT adds 29 lawyers creating one of the largest practices of its kind in the UK

TLT grows projects infrastructure and construction team with appointment of new partner
TLT Partner Appointed Chair of North West Fraud Forum | TLT

TLT Shortlisted for Firm of the Year at Scottish Legal Awards | TLT

TLT Wins Law Firm of the Year at Manchester Legal Awards | TLT

TLT Recognised for Two Awards at The Lawyer Awards 2022 | TLT

TLT Shortlisted for Two Manchester Legal Awards 2022 | TLT

TLT advises Network Homes on £140m sale to Grainger

TLT advises One Housing Group on major affordable housing project

TLT advises Town and Country Housing on modular homes acquisition

TLT completes largest office acquisition on record in Northern Ireland

Preparing for the Procurement Act 2023 - construction industry focus

%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.jpg)











%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi.avif)




