
Infrastructure Planning Blog
62: The end of the challenges to expansion of Luton and Gatwick Airports
Today's entry looks at the end of the runway for the challenges to the Luton Airport and Gatwick Airport Development Consent Orders (DCOs), and at reforms to judicial review relating to indemnities.
Nothing beats a Jet2 holiday
The Supreme Court has refused permission to appeal the legal challenge to the Luton Airport DCO. This follows the judgment of the Court of Appeal holding that the claimants had simply missed the deadline (see Blog 31 and this summary).
This is a huge victory for our client Luton Rising and brings to an end a 15-month saga since the DCO was made by the Secretary of State. Hurrah!
Meanwhile, permission to appeal has also been refused in relation to the legal challenge to the Gatwick Airport DCO. Blog 56 covered the substantive judgment of the High Court, which was the subject of this appeal. The claimants fared no better here, with the Court concluding that "each of the grounds of appeal raised by each appellant is unarguable. Neither appeal has a real prospect of success." The judgment is quite bruising. "Far-fetched" is just one of the many adjectives used.
Rather than cover the judgment in full, here are some of the highlights and differences between the High Court and Court of Appeal decisions.
On the alleged misinterpretation of whether the Airports National Policy Statement (ANPS) supported expansion at Gatwick, the two judgments are largely aligned. This was always a rather fanciful argument, given the plain wording of paragraphs 1.29 and 1.42 of the ANPS. However, the Court of Appeal was particularly robust in concluding that "there is no cap on the scale of proposals that can be brought forward under the ANPS and MBU policy and in particular proposals which would lead to an increase of in excess of 10 mppa are expressly contemplated". That is a useful finding for other airports seeking expansion.
In relation to the assessment of greenhouse gas (GHG) emissions, one ground of appeal concerned an alleged inconsistency with an earlier judgment in Boswell. In that case, the court held that "the Secretary of State was entitled to find that the proposal accords with NPS EN-1 and is compatible with the trajectory to ‘net zero’ and, in relation to section 6.3 of the IEMA guidance, the Secretary of State should have assessed the GHG emissions as having a less than significant adverse effect".
The claimants' argument in Gatwick appears to have been that, because the Secretary of State had found significant effects and had not concluded that the proposal was compatible with the trajectory to net zero, there should necessarily have been a finding of a material impact on the UK's net zero targets, consistent with Boswell. In what is perhaps about as blunt as judges get, the Court of Appeal held that the claimants had "not read that [Boswell] paragraph properly".
While you recover from that judicial chokeslam, perhaps with Fix Up, Look Sharp by Dizzee Rascal playing in the background, the reason was straightforward. The Court explained that "a proposed development may not be fully compatible with the UK's net zero trajectory, as the SST found to be the case here, but still not materially impact upon the UK's ability to meet its net zero target and carbon budgets".
There is also a useful reaffirmation of the principle that quantitative information is not always required for the purposes of Environmental Impact Assessment (EIA). The attempt to argue that the precautionary principle required further quantitative analysis "adds nothing", according to the Court. See paragraph 68 for further confirmation.
Paper planes
Speaking of judicial review, we have made no secret on these pages of our support for the Government's attempts to curtail the misuse of judicial review. The Government is progressing further reforms in this area. One of those announced in May 2026 was that "in response to the Fingleton [Nuclear Taskforce] Review, the Government has committed to...developing a government-backed indemnification scheme to give developers greater financial certainty when facing legal challenge".
While recommended by the Nuclear Taskforce, this reform is not entirely new. Variations of the concept have been circulating in think-tank circles for several years, and a version of it was even introduced for certain CCUS projects.
Perhaps I am biased, but there is a compelling and neat logic behind the proposal: the delay caused by judicial review proceedings can itself create significant value for those seeking to obstruct development. By reducing the financial consequences of such delays and covering costs associated with commencing works, the proposed indemnification scheme would remove much of that incentive. In particular, it may help deter the more speculative or fanciful challenges that are brought primarily to delay.
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at August 2026. For more information see our terms & conditions.
Get in touch
Get in touch
Insights & events

Infrastructure Planning Blog 62: The end of the challenges to expansion of Luton and Gatwick Airports

Infrastructure Planning Blog 61: More updates to PINS' advice

Infrastructure Planning Blog 60: New Secretaries of State, NPS consultations, PINS advice and local authorities

Beyond the Building Safety Act: Fire safety remediation works outside the statutory regime

Infrastructure Planning Blog 59: A solar decision, revised National Policy Statement for Ports and other news

Infrastructure Planning Blog 58: Guidance, judgment and decision

Infrastructure Planning Blog 57: An environmental judgment and a consented solar farm

Contribution claims, vicarious liability, and Unfair Contract Terms Act: lessons from Sutton and East Surrey Water Plc v Monarch Chemicals and Muztrans Ltd

Infrastructure Planning Blog 55: Goodbye statutory consultation and other planning infrastructure news

Infrastructure Planning Blog 52: Changes to Habitats Regulations, application fees, a parliamentary petition, and a solar farm refusal

Infrastructure Planning Blog 51: A veritable fountain of infrastructure planning news

London Luton Airport expansion finally cleared for take-off?

Infrastructure Planning Blog 50: An offshore wind DCO, safeguarding transmission and the King’s Speech

Infrastructure Planning Blog 49: Sundowner and BNG on the up

Building Liability Orders: First fully contested judgment on BLOs delivers clarity

Infrastructure Planning Blog 48: Legal challenge ruled totally without merit, pollution control regimes and football stadiums

Impact of flexible working on towns and cities - the market and legal considerations

Nick Evans joins TLT as partner placing the firm at the helm of infrastructure, planning, public law and future energy in the UK

TLT expands future energy and infrastructure expertise with new Partner appointment

TLT strengthens public sector infrastructure and future energy offering with two new partners

TLT strengthens construction expertise with third partner hire in six months

TLT adds 29 lawyers creating one of the largest practices of its kind in the UK

TLT grows projects infrastructure and construction team with appointment of new partner
TLT Partner Appointed Chair of North West Fraud Forum | TLT

TLT Shortlisted for Firm of the Year at Scottish Legal Awards | TLT

TLT Wins Law Firm of the Year at Manchester Legal Awards | TLT

TLT Recognised for Two Awards at The Lawyer Awards 2022 | TLT

TLT Shortlisted for Two Manchester Legal Awards 2022 | TLT

TLT advises Network Homes on £140m sale to Grainger

TLT advises One Housing Group on major affordable housing project

TLT advises Town and Country Housing on modular homes acquisition

TLT completes largest office acquisition on record in Northern Ireland

Preparing for the Procurement Act 2023 - construction industry focus






%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.jpg)







%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi.avif)






