
Infrastructure Planning Blog
44: Plans, purdah and publication
Today’s entry looks at the implementation plans for the Planning and Infrastructure Act 2025, DCO delays, and the publication of a recommendation report relating to a withdrawn DCO project.
PIA not MIA
The Government has published an update on its implementation plans for the Planning and Infrastructure Act 2025. The biggest takeaway is the confirmation that guidance covering pre-application, acceptance, and content of a DCO application will be published “Spring to Summer 2026”. That target is also when the secondary legislation covering the power to disapply the requirement for development consent (i.e., the “opt-out”), and rights of entry to land for surveys measure will be laid.
The secondary legislation relating to material/non-material changes to DCOs (and, specifically, the removal of the distinction between material/non-material changes) is not due until 2027. Interestingly, the updated guidance on pre-examination will “reflect the increased importance of the Examining Authority’s Initial Assessment of Principal Issues (IAPI)”. I’ve always thought the IAPI is a bit like the Holy Roman Empire (neither Holy, nor Roman), in that it does not usually present an assessment of any principal issues, and is usually generic and never referred to again. It should be more than an initial assessment, and it should highlight resolved matters and not just unresolved issues so its welcome this is being updated.
The Government has also said that it will be laying secondary legislation which will enable cost-recovery for local authorities. I have some strong reservations about cost recovery, and think it can be used to perversely to increase costs and protract disagreements. Previous Government-commissioned reports had warned against this (see, for example, paragraph 490 here). It’s hoped that any secondary legislation will try to limit its potential use to what is strictly required.
Meanwhile, a separate document relevant to the conventional planning regime published by Government confirms that for “Applications relating to land owned or leased by the Nuclear Decommissioning Authority (or one of its subsidiaries) [and] Applications relating to nuclear fuel cycle facilities, including facilities for uranium conversion, enrichment, deconversion, nuclear fuel manufacture, or associated production processes” that the “consultation direction” applies. The consultation direction requires a local planning authority to consult the Secretary of State where local planning authorities are minded to refuse planning permission.
Purdah she wrote
The Secretary of State has announced three delays to offshore wind-related projects this week:
- North Falls Offshore Wind has been delayed from 28 April to 14 May
- Morgan and Morecambe Offshore Wind onshore transmission assets has been delayed from 29 April to 14 May
- Dogger Bank South Offshore Wind has been delayed from 30 April to 14 May
The Written Ministerial Statement states that the delay is because “current statutory dates for these three cases are within the pre-election period for local elections in England”. The guidance on the pre-election period (formerly known as purdah) states that particular care should be taken where there is a specific local or geographical dimension to an announcement; where an announcement could have a particular impact on an area or areas where elections are being held; and where an announcement relates to matters which are likely to be raised in election campaigns.
This line of thought has not always been followed in pre-election periods, but it’s worth considering the case law on this point. The starting point is that this convention is “not a principle of law... does not provide ministers with a defence to proceedings in private or public law [and..] it is in no sense binding on the courts" and it, instead, "is convention" (per R (on the application of ClientEarth) v Secretary of State for Environment, Food and Rural Affairs [2017] EWHC B12 (Admin)).
I’m aware of only one recent case where the grant of a planning permission was challenged in the pre-election period. In R (Lewis) v Redcar and Cleveland Borough Council [2009] 1 W.L.R. 83), a decision to grant planning permission was made during the pre-election period. The accusation was that the decision was in some way pre-determined, and influenced by wanting to brag about the permission during the election. The Court of Appeal determined the mere fact there was an overlap between the pre-election period, and the grant of permission, was not sufficient to render the decision unlawful.
H2Teeside Revisited
Readers will recall that the promoter of H2Teesside withdrew their application for development consent shortly before the Secretary of State was due to make a decision on the application. The reason for that withdrawal was an unresolvable conflict between the proposed hydrogen project, and data centre proposals put forward by the local development corporation.
The Planning Inspectorate has published the Recommendation Report notwithstanding that withdrawal. The ExA recommended approval for the project. While we’ll never know exactly what the Secretary of State would have decided, it’s worth having a look at some of the issues that arose, particularly in relation to greenhouse gas emissions, as well as the various principles applied in the context of protective provisions negotiations. On the former, unsurprisingly, the well trodden arguments challenging the adequacy of standardised assessments were given very short shrift indeed!
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at March 2026. Specific advice should be sought for specific cases. For more information see our terms & conditions.
Get in touch
Get in touch
Insights & events

Building Liability Orders: First fully contested judgment on BLOs delivers clarity

Infrastructure Planning Blog 48: Legal challenge ruled totally without merit, pollution control regimes and football stadiums

The UK Carbon Border Adjustment Mechanism and potential impacts on projects

Infrastructure Planning Blog 47: Overhead line changes, and enabling data centres

Infrastructure Planning Blog 46: BNG for NSIPs defined but delayed and other news

Infrastructure Planning Blog 45: Largest solar DCO granted and other news

Infrastructure Planning Blog 44: Plans, purdah and publication

Infrastructure Planning Blog 43: Slow, slow, quick, no go for infrastructure planning

Infrastructure Planning Blog 42: Nuclear reforms, discharge of requirements and NPPF changes

Infrastructure Planning Blog 41: New Welsh guidance, the use of AI in planning and other updates

Northern Ireland Planning and Environment update: Minerals

Infrastructure Planning Blog 40: A conference and another revocation

Infrastructure consent order regime in Wales: Updates

Infrastructure Planning Blog 39: Fenwick Solar Farm, Sizewell C and EIA case law

Infrastructure Planning Blog 38: A new wind DCO, and European streamlining

Infrastructure Planning Blog 37: Fission 'n' chippy

Impact of flexible working on towns and cities - the market and legal considerations
1 September – all change (again) for the Community Infrastructure Levy

Nick Evans joins TLT as partner placing the firm at the helm of infrastructure, planning, public law and future energy in the UK

TLT expands future energy and infrastructure expertise with new Partner appointment

TLT strengthens public sector infrastructure and future energy offering with two new partners

TLT strengthens construction expertise with third partner hire in six months

TLT adds 29 lawyers creating one of the largest practices of its kind in the UK

TLT grows projects infrastructure and construction team with appointment of new partner

TLT hires transport and renewable energy specialist supporting the expansion of its planning team
TLT Partner Appointed Chair of North West Fraud Forum | TLT

TLT Shortlisted for Firm of the Year at Scottish Legal Awards | TLT

TLT Wins Law Firm of the Year at Manchester Legal Awards | TLT

TLT Recognised for Two Awards at The Lawyer Awards 2022 | TLT

TLT Shortlisted for Two Manchester Legal Awards 2022 | TLT

TLT advises Network Homes on £140m sale to Grainger

TLT advises One Housing Group on major affordable housing project

TLT advises Town and Country Housing on modular homes acquisition

Biodiversity Net Gain: What’s changing and what it means for you

Preparing for the Procurement Act 2023 - construction industry focus

BNG - TLT and Belmont Estate talk nature positivity

What does the next generation of our cities look like?





%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.avif)


%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.jpg)
















