Today's entry looks at changes and updates from Natural England and the Environment Agency, and provides a little list of small things that could mean a lot.
Little things that mean a lot
I recently came across a list by former Prime Minister Harold Wilson titled "Little Things That Mean A Lot" which includes erudite things like "the future of the pint," "juggernauts", and the "abolition of hare coursing." It got me thinking: what are the small things that would make a significant difference in the operation of the nationally significant infrastructure project (NSIP) regime? Here's a starter for ten.
- Detailed Hearing Agendas: if you have worked in the NSIP regime for any period of time, and you see a proposed hearing for '[insert vague word here] matters', your heart probably sinks. Which matters? Which experts do we need to make sure are there? How will interested parties know that the issues they care about most will or will not be raised so that they can take annual leave if necessary? How will statutory bodies know if the hearing will relate to their functions? Providing a clear indication, before detailed agendas are issued, would mean a lot and would probably reduce the overall anxiety in the regime.
- Robust cost measures: the Planning Act 2008 contains provisions relating to the award of costs. Those provisions are not oft-used, and recent examples of them being invoked have involved allegations that a promoter has behaved unreasonably in the context of withdrawn applications. But, particularly with the use of AI, there has been a deluge of representations involving significant copying and pasting, as well as hallucinations which send examinations off on frolics and generate unnecessary additional questions. A more robust willingness to use the costs regime where parties behave unreasonably might help concentrate minds.
- Cost recovery guidance: we made our views known on cost recovery here, but guidance on what is reasonable would really assist both developers and local authorities in understanding what can be recovered. Preferably, there would be fairly firm limits on the use of external resources. I am afraid that if these costs are not controlled appropriately, it will be a red cross against the DCO regime being utilised.
- Consistency in DCO drafting: similar in spirit to the ‘future of the pint’, it would be helpful to see greater consistency in DCO drafting, while retaining appropriate flexibility, particularly where that flexibility enables environmentally better outcomes. Inconsistency, or a lack of flexibility, does not just make drafting more difficult: it can prevent better outcomes. Transport DCOs have, after quite a lot of applications, landed in broadly the right place on this point.
- Shutting things down: as part of the trials on the Initial Assessment of Principal Issues, it would be great to see a forthright 'closing down' of issues during the examinations. This would involve Examining Authorities saying 'we've heard enough on that, thanks very much.'
None of these require primary legislation. All of these would reduce the complexity, cost and burden for interested parties, promoters and regulators.
Focus
Earlier this month, changes to how Natural England will interface with planning decisions were announced. Natural England will now focus on proposals presenting the greatest risks or opportunities for nature, including complex and strategic cases. The idea is to move away from repeatedly advising on more routine applications where established guidance or upfront advice already exists, allowing Natural England to engage earlier and concentrate its resources on resolving significant environmental issues. Standing advice and guidance will instead play a greater role in helping local planning authorities deal with routine matters.
There is an important limitation for infrastructure practitioners: the legislative change underpinning the new approach, made by the Planning and Infrastructure Act 2025 to Natural England's duty under section 4 of the Natural Environment and Rural Communities Act 2006, applies only to planning casework under the Town and Country Planning Act 1990. In other words, this is not itself a change to Natural England's role in the DCO regime.
Permit me
The Environment Agency updated its guidance on the sometimes-tricky relationship between planning permission and environmental permitting on 19 October. The guidance explains the three different positions the Environment Agency can take where a development also requires an environmental permit, when it may recommend use of its pre-application services and, perhaps most interestingly, when it considers that the planning and permitting applications should be “parallel tracked”. There is also now a specific section dealing with NSIPs.
None of this changes the fundamental separation between the two regimes: planning considers whether the development is an acceptable use of the land, while permitting considers whether the activity can be constructed or operated so as to prevent or minimise environmental impacts. But the updated guidance is a useful reminder for DCO projects that the two processes do not exist in splendid isolation.
Most importantly, it re-emphasises the Gateshead principle that where a matter is controlled under one regulatory regime, a separate one should not seek to duplicate or replicate it. This will be very important for co-located data centres/power generation coming forward. It is not necessary, appropriate or even reasonable to re-impose requirements in respect of impacts which are appropriately controlled elsewhere. In that context, the DCO application should instead demonstrate that the relevant impacts have been appropriately assessed and explain how they will be controlled through the other regulatory regime.
Spatial awareness
The Department for Energy Security and Net Zero has formally given the National Energy System Operator a little more breathing room on the first Strategic Spatial Energy Plan (SSEP). A direction published on 23 October moves the deadline for submitting the first SSEP to the Secretary of State from 31 December 2026 to 31 December 2027. The Government says the change formally reflects the revised timetable announced on 4 December 2025.
The SSEP is an important part of the increasingly strategic approach to planning Britain's energy infrastructure, so the extra year is noteworthy for anyone involved in bringing forward major energy projects. The extension applies only to the first SSEP: Ofgem intends to consult during 2027 on changes to the relevant licences dealing with the timing of subsequent SSEP cycles and related strategic energy planning processes. So, spatial energy planning is still coming, just rather less imminently than the original deadline suggested.
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at October 2026. Specific advice should be sought for specific cases. For more information see our terms & conditions.
Get in touch
Related services
Get in touch
Insights & events

Infrastructure Planning Blog 73: Regulating regulators

Infrastructure Planning Blog 72: Latest solar DCO decision analysed

Belong v Seddon: Can PCSA liabilities survive following execution of a JCT contract?

Northern Ireland Planning and Environment update: Energy

Infrastructure Planning Blog 70: Statistics on major projects, tech updates, and applying the new NPPF

Infrastructure Planning Blog 69: Application stocktake as changes to the Planning Act 2008 regime start to take effect

Infrastructure Planning Blog 68: Morecambe and a wise decision?

Adjudication Enforcement in Focus: When is an Agreement Agreed?

Infrastructure Planning Blog 67: Put out more flags

Infrastructure Planning Blog 66: Full BNG for NSIPs guidance published

Infrastructure Planning Blog 65: A beacon of light

Infrastructure Planning Blog 64: What does the updated National Planning Policy Framework mean for infrastructure?

Infrastructure Planning Blog 63: Harry Potter and the grave error

Infrastructure Planning Blog 62: The end of the challenges to expansion of Luton and Gatwick Airports

Infrastructure Planning Blog 61: More updates to PINS' advice

Impact of flexible working on towns and cities - the market and legal considerations

Nick Evans joins TLT as partner placing the firm at the helm of infrastructure, planning, public law and future energy in the UK

TLT expands future energy and infrastructure expertise with new Partner appointment

TLT strengthens public sector infrastructure and future energy offering with two new partners

TLT strengthens construction expertise with third partner hire in six months

TLT adds 29 lawyers creating one of the largest practices of its kind in the UK

TLT grows projects infrastructure and construction team with appointment of new partner
TLT Partner Appointed Chair of North West Fraud Forum | TLT

TLT Shortlisted for Firm of the Year at Scottish Legal Awards | TLT

TLT Wins Law Firm of the Year at Manchester Legal Awards | TLT

TLT Recognised for Two Awards at The Lawyer Awards 2022 | TLT

TLT Shortlisted for Two Manchester Legal Awards 2022 | TLT

TLT advises Network Homes on £140m sale to Grainger

TLT advises One Housing Group on major affordable housing project

TLT advises Town and Country Housing on modular homes acquisition

TLT completes largest office acquisition on record in Northern Ireland

Preparing for the Procurement Act 2023 - construction industry focus




%20790px%20X%20451px%2072ppi.jpg)

%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.jpg)







%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi.avif)