Infrastructure Planning Blog

77: DCO progress and harbour reforms

This week's entry provides an update on the current and anticipated Development Consent Order (DCO) pipeline and the British Port Association's (BPA) paper on much-needed reforms to the Harbour Order process.

DCO update

After a flurry of decisions and legal challenges reported in last week's blog and with the end of the year approaching, we thought it might be helpful to take stock of the current pipeline of DCOs in the system.

Here it is:

Stage Project(s) Comment
Acceptance Two – Eastern Green Link 3 and 4 and Kingsway Solar Farm The latter was submitted and withdrawn in July, as reported in blog 55. Both acceptance decisions are due next week.
Pre-examination Two – Lighthouse Green Fuels Project and North Humber to High Marnham No date for the preliminary meeting has been set. The former has received a request to address "several significant matters" (see here), so it might be a while before that examination gets going.
Examination Six – Meridian Solar Farm, Light Valley Solar, East Pye Solar, Whitestone Solar Farm, Oxfordshire Strategic Rail Freight Interchange and Hampshire Water Transfer and Water Recycling Project None of these will reach the end of the examination in 2026. The first to do so will be Light Valley Solar at the end of January 2027.
Recommendation Six – East Midlands Gateway Phase 2, East Park Energy, Tween Bridge Solar Farm, Rosefield Solar Farm, Lime Down Solar Project, the Droves Solar Farm There is a material change application at recommendation stage too: the East Midlands Rail Freight Interchange Material Change. Only one material change application has been granted under the Planning Act 2008 so far, for Able Marine Energy Park.
Decision Five – Fosse Green Energy, Connah's Quay Low Carbon Power Project, Keadby Next Generation Power Station, AQUIND Interconnector and Norwich to Tilbury Only two decisions – Connah's Quay and Keadby – are due before the end of the year.
Legal challenge Two – Beacon Fen Energy Park and Dogger Bank South Offshore Wind Farms Hearing dates are to be confirmed. That's now six challenges to the 16 DCOs granted since the rules for challenging decisions on nationally significant infrastructure projects were changed, so those changes don't appear to have stopped claimants having a go at least, though none have been successful since the reforms.

The pipeline of anticipated submissions is strong – PINS' register currently identifies three projects with a Q4 2026 submission date (Future Energy Llanwern Solar Project, White Horse Reservoir and the Trelavour Lithium Project) and some 49 projects with anticipated submission dates falling before the end of 2027.

Solar continues to dominate, accounting for more than 50% of those currently in the system (acceptance, through post-decision/legal challenge) and a third of anticipated submissions through to the end of 2027. Some of the first data centre DCO applications will start to land in the first half of 2027.

Seas the Day

The BPA has published a reform paper examining how the Harbour Order regime could be made more effective, proportionate and capable of supporting the modernisation of UK ports.

A Harbour Order is a form of statutory instrument made under the Harbours Act 1964, obtained (in England) on application to the Marine Management Organisation (MMO). It enables harbour authorities to amend or update their powers to operate, develop and manage their harbours effectively.

Harbour Revision Orders (HROs) amend existing harbour legislation; Harbour Empowerment Orders (HEOs) establish or empower new harbours and authorities. Both can authorise harbour works, though where those works constitute nationally significant infrastructure, the appropriate route is a Development Consent Order rather than a Harbour Order.

The BPA's main finding is that the current Harbour Order process is not working satisfactorily. The MMO's own guidance advises applicants that an order can take four to five years from receipt to determination, even for relatively straightforward applications to modernise powers that will often use similar language and clauses. The Port of Neath (Tidal Lagoon) HRO was, for example, made nearly eight years after the application was submitted.

The BPA identifies a core structural problem: the regime is being asked to process major works applications through the same machinery as comparatively straightforward powers updates. Individual harbour authorities also begin from very different statutory positions depending on the age and history of their legislation, so powers that are routine for one modernised authority may require another to obtain a full HRO.

The paper recommends reform across three areas: process, reducing demand and clearing the backlog:

  • On process, key measures include removing routine Parliamentary laying, which currently adds at least three months; developing a publicly available library of standard clauses; and establishing a clearer hierarchy of examination methods, with written representations as the default and public inquiries reserved for genuinely complex disputes.
  • On reducing demand, the recommendation is for Government to legislate to provide harbour authorities with a modern set of generally available statutory powers, covering management, land acquisition, subsidiaries, borrowing, energy services, harbour directions and byelaw-making, removing the need for a Harbour Order to obtain them.
  • On clearing the backlog, the paper calls for a dedicated, time-limited recovery team to drive older applications to completion, with transparent progress reporting on the total number of live applications, their age and stage, and the net change in the caseload over time.

This paper is a welcome step forward towards the long-overdue modernisation of a process that has become far too slow, and it sits squarely alongside the Government's push to streamline consenting and speed delivery of major infrastructure under the Planning and Infrastructure Act 2025.

This publication is intended for general guidance and represents our understanding of the relevant law and practice as at November 2026. Specific advice should be sought for specific cases. For more information see our terms & conditions.

No items found.

No items found.

Date published
20 Nov 2026
TLT website banner

Sign up to the mailing list to receive the Infrastructure Planning Blogs

Abstract overlapping curved shapes in varying shades of violet and purple on a solid violet background.

Legal insights & events

Keep up to date on the issues that matter.

Abstract yellow background with overlapping translucent olive green curved shapes.

Follow us

Find us on social media

No items found.