78: First BNG NSIP, acceptance trends and other news

This week's entry covers the first nationally significant infrastructure project (NSIP) application subject to mandatory biodiversity net gain (BNG), some seemingly more onerous post-acceptance obligations coming from the Planning Inspectorate, mooted mergers/abolitions of relevant statutory bodies and a consultation on devolving Transport and Works Act Order (TWAO) processes.

First BNG NSIP

The White Horse Reservoir Development Consent Order (DCO) application was made on 19 November 2026, making it the first one subject to mandatory BNG.  As the name suggests, this application is for a new reservoir, which is in the Vale of the White Horse near Abingdon in Oxfordshire. It has had various previous names such as the Abingdon Reservoir and SESRO (the South East Strategic Reservoir Option).

The additional application document, namely the outline biodiversity gain plan, and the new requirements in the draft DCO to address BNG will no doubt be studied with interest across the infrastructure sector, but they won't be published until the application is accepted, which must be by 17 December. I am personally looking forward to the reservoir being described as a 670-hectare pond habitat.

Post-consent obligations

The last two DCO applications to be accepted at the time of writing have had significant letters issued by their Examining Authorities under section 89(3) of the Planning Act 2008, which allows procedural decisions not related to the Initial Assessment of Principal Issues or the discussion at the Preliminary Meeting, and which can be issued at any time. Both are about habitats issues.

The one for the North Humber to High Marnham grid connection project is here. This letter 'strongly advises' that the applicant comprehensively improves the Habitat Regulations Assessment Report (HRAR) by the relevant representation deadline (which is now set by the applicant as 5 January 2027). It then goes on to say 'The Rule 6 letter, inviting persons to the Preliminary Meeting, will not be issued until such time as the ExA is content that the HRAR is sufficiently developed and evidence that Natural England have engaged and endorsed the approach taken.'

The one for the Lighthouse Green Fuels project in Teesside is here. This time the applicant is asked to provide a revised HRAR before the relevant representations period opens. Other issues are raised too. The letter ends by saying 'It is important to note that in the absence of the requested information, the ExA could postpone or adjourn the PM until such a time that it has been provided.'.

It is good that applications are being accepted where issues like these are outstanding, but is threatening to delay the preliminary meeting until they've been resolved an appropriate approach? One for discussion.

Quango news

On Monday, First Secretary of State Louise Haigh MP gave a keynote speech to the Confederation of British Industry (CBI) annual conference in London. You can find the text of the speech here.

The part picked up by the media is the following:

'And as part of rewiring the state we will reform arm’s length bodies to increase public control. We will take a look at each of their functions and pose the challenge: what should be devolved, what can be dissolved and what could be delivered [by] departments. We’ve already begun that process with the Environment Agency, Natural England, Ofwat and the Drinking Water Inspectorate.'

This has been interpreted as abolishing Natural England, which is not singled out in the speech but may have been the subject of associated briefings. An open letter in response was swiftly written and signed by over 40 environmental bodies.

TWA devolution consultation

The government has launched a consultation on devolving the ability to approve applications for Transport and Works Act Orders to Mayoral Strategic Authorities (MSAs), which you can find here. The closing date is 18 December 2026.

The consultation contemplates automatic devolution to all MSAs and management of the process by MSAs. It also considers how to deal with cross-boundary TWAOs, the ability to refer to central government, the form and mechanism for granting a TWAO, what support MSAs would need for this and whether there should be one fee structure or MSAs should set their own fees.

And finally, one of the images in this submission relating to the Meridian solar DCO application will make you laugh. [Update: sadly, the offending image has now been redacted].

This publication is intended for general guidance and represents our understanding of the relevant law and practice as at November 2026. Specific advice should be sought for specific cases. For more information see our terms & conditions.

No items found.

No items found.

Date published
27 Nov 2026
TLT website banner

Sign up to the mailing list to receive the Infrastructure Planning Blogs

Abstract overlapping curved shapes in varying shades of violet and purple on a solid violet background.

Legal insights & events

Keep up to date on the issues that matter.

Abstract yellow background with overlapping translucent olive green curved shapes.

Follow us

Find us on social media

No items found.