
NGESO signals plans to widen scope of connection process reform
In their April update, NGESO clarified the proposal in respect of the existing queue.
They propose a window ahead of January 2025 during which existing projects can submit evidence to demonstrate that they have met the Gate 2 criteria.
For projects that meet the criteria, either the existing connection date would be confirmed or there would be an opportunity to seek an acceleration of this date (where capacity becomes available due to the queue reducing). These projects which pass Gate 2 would be allocated User Commitment liabilities and securities and would have Queue Management Milestones applied. Moving forward these milestones must be met or the project may risk being removed from the queue under the new NGESO powers (arising out of CMP376).
For projects that cannot demonstrate the Gate 2 criteria, the connection date and connection point in their existing construction agreements would become merely indicative. Where applicable, User Commitment liabilities and securities would no longer be required, and the projects would not be subject to any Queue Management Milestones.
The absence of a confirmed connection date and connection point for projects remaining in Gate 1 would leave them open to the risk that another project could be able to overtake them by demonstrating compliance with Gate 2 criteria. NGESO have acknowledged industry concerns that this could create inequality between technologies and favour smaller, agile and less land-intensive projects. In response, NGESO have indicated that the criteria for Gate 2 may vary slightly for different technologies, proposing that this would mean a more level playing field in the race to reach Gate 2 and secure a connection date. However, such variations would also put on the table the prospect of the Gate 2 criteria applying differently to different technologies and thereby preferring some technologies over others.
For those looking ahead to future applications, the new process will form a key part of their approach to connection. NGESO propose that TMO4+ will be run in annual cycles with application windows during which projects can apply to pass Gate 1. It is then proposed that projects will be grouped together for Gate 2 assessment by NGESO regularly throughout the year.
Developers may wish to explore the implications of the new process on financing options and on their strategy and timeframe for seeking various permissions in respect of potential projects.
NGESO have indicated that the TMO4+ process is anticipated to affect embedded projects in the distribution network. For certain 'Large' projects the new application process would be directly applicable and such projects would be expected to follow TMO4+ closely. At present there is a definition of 'Large' derived from the Grid Code which applies different capacities in different parts of the country and is used to determine whether a distribution connected project must have a BEGA or a BELLA. The same thresholds are proposed here.
For small- to medium-sized projects, the impact of TMO4+ has yet to be clarified. NGESO have signalled that Distribution Network Operators (‘DNOs’) would be allocated Distribution Forecasted Transmission Capacity (‘DFTC’). The DNOs would then manage connection applications for prospective projects and allocate the DFTC to such projects accordingly.
What comes next
Get in touch
Get in touch
Insights & events

Infrastructure Planning Blog 29: The Nuclear Regulatory Review, Data Centres and Heathrow third runway

Infrastructure Planning Blog 27 - High Court cases, the Nuclear NPS and the Planning & Infrastructure Bill latest

Infrastructure Planning Blog 25 - A solar DCO, data centres, carbon budgets and other updates

Infrastructure Planning Blog 17 - Data centres: infrastructure planning reforms with a bit of byte

Nick Evans joins TLT as partner placing the firm at the helm of infrastructure, planning, public law and future energy in the UK









































