
Reforms to MHCLG’s Compulsory Purchase Guidance 2026: Implications for promoters and landowners
On 17 June 2026, the Ministry of Housing, Communities and Local Government (MHCLG) published its updated ‘Compulsory Purchase Process: Guidance’ (Guidance), replacing the January 2025 edition. The updated Guidance signals a more flexible approach for promoters progressing complex projects, particularly around conditional confirmation of Compulsory Purchase Orders (CPOs). Although the Guidance does not fundamentally change the underlying legal tests, the revisions will allow CPOs to be confirmed subject to conditions, enabling promoters to progress schemes while resolving outstanding matters. In turn, this is expected to reduce delays, avoid the need for re-determination, and support more timely delivery of complex projects.
Key takeaways
1. Conditional confirmation of Compulsory Purchase Orders
The most significant development in the revised Guidance is the explicit recognition of conditional confirmation of CPOs. The Guidance provides that the confirming authority (CA), as defined under paragraph 28 of the Guidance, may conditionally confirm a CPO even where impediments remain outstanding, subject to the imposition of ‘pre-exercise conditions’ under s.13BA of the Acquisition of Land Act 1981 (ALA 1981). A CPO may be conditionally confirmed where the CA considers that the acquiring authority (AA) has established a compelling case in the public interest but there remains an outstanding impediment to the delivery of the underlying scheme which could be overcome by imposing a pre-exercise condition(s). In practice, this marks a shift away from an “all or nothing” approach at the point of confirmation. Rather than refusing an order where impediments remain, confirming authorities may now allow schemes to proceed subject to clearly defined conditions. This enables promoters to manage residual risks post‑confirmation, maintain programme momentum, and avoid delay associated with re-making or re-submitting orders.
Where the CA considers the imposition of pre-exercise conditions in granting conditional confirmation for a CPO, it must first give both the AA and any objectors the opportunity to make representations. There is no prescribed or standard time limit for AAs to satisfy these pre-exercise conditions. The Guidance clarifies that pre-exercise conditions should:
- be used sparingly to overcome a clear obstacle to delivery;
- be capable of being fulfilled by the AA;
- be clear, concise and worded objectively;
- not duplicate planning regime conditions; and
- be used in limited and exceptional circumstances.
The Guidance also clarifies that pre-exercise conditions should not be imposed where the:
- CPO is already fully justified and a compelling case in the public interest exists;
- condition deals with matters unrelated to land acquisition; or
- condition relates to compensation assessment or determination which is governed by a separate legal framework
The CA will issue a decision letter that confirms the conditionally confirmed CPO, the pre-exercise conditions imposed, the deadline for AA to apply to confirm compliance and the reasons for imposing those conditions. The statutory notice which must be served and affixed to land by the AA under s.15 ALA 1981. Relevant objectors can make written representations in response to the application but can only comment on whether the pre-exercise conditions have been met. The conditional confirmation is provisional, and the CPO cannot be implemented until all the pre-exercise conditions are satisfied and formally confirmed by way of a fulfilment notice. Where the CA is satisfied that the AA has met the pre-exercise conditions, and makes the CPO, the AA must serve a copy of the CPO and the fulfilment notice on affected persons, affix the notice on the land, and publish the notice in a local newspaper.
The CA has powers to extend the usual time limit for exercising CPO powers. This applies for both the notice to treat and general vesting declaration (GVD) routes. Normally, at least 3 months’ notice must be given before taking possession under a GVD, however earlier possession is permitted in exceptional circumstances where:
- the land is unoccupied (or occupied unlawfully);
- it is unfit for ordinary use due to disrepair, neglect, contamination etc; and
- no person with an interest is able to serve a counter-notice.
Where all three conditions are satisfied, possession can be accelerated to a 6-week timeframe. A person may challenge the AA’s decision, and the AA must provide a written response on receiving the challenge notice. If challenged correctly, the AA must amend the GVD and revert to the three-month notice period, notifying those impacted by the GVD.
2. Electronic service of notices
Electronic service of compulsory purchase documentation is now permitted in certain contexts through delivery to an e-mail address or uploading it to a website (instead of physical delivery) provided that the recipient has agreed in writing to receive notices or documents through such electronic means. It is important for AAs, CAs, inspectors, local authorities, and statutory undertakers to note that they may be served notices or documents electronically, even where they have not specifically agreed in writing, where certain conditions are met as listed under paragraph 25.6 of the Guidance. Affected parties should therefore ensure that robust internal processes are in place to monitor and manage electronic communications, including designated inboxes, clear responsibility for reviewing incoming notices, and prompt escalation procedures to avoid missing key procedural steps or deadlines.
The Guidance also provides further information on advance payments of compensation, decision powers to confirm CPOs, engagement, and mitigation which are not considered as part of this article.
Taken together, the updates signal a move towards a more delivery-focused approach to compulsory purchase, where the emphasis is on managing – rather than eliminating – risk at the point of confirmation. This is likely to benefit well-prepared promoters, while requiring landowners to adapt how and when they raise objections.
Author: Jebaraj Jebakumar
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at June 2026. For more information see our terms & conditions.
Get in touch
Get in touch
Insights & events

Reforms to MHCLG’s Compulsory Purchase Guidance 2026: Implications for promoters and landowners

Infrastructure Planning Blog 56: The failed judicial review of the Gatwick Airport expansion

Infrastructure Planning Blog 55: Goodbye statutory consultation and other planning infrastructure news

Infrastructure Planning Blog 54: A new draft national policy statement and a solar misapprehension

Infrastructure Planning Blog 53: Biodiversity net gain for nationally significant infrastructure projects, and more

A change in the wind: How planning reforms are powering onshore wind development

Hydrogen projects: navigating planning policy in the absence of a settled national strategy

Infrastructure Planning Blog 52: Changes to Habitats Regulations, application fees, a parliamentary petition, and a solar farm refusal

Infrastructure Planning Blog 51: A veritable fountain of infrastructure planning news

London Luton Airport expansion finally cleared for take-off?

Infrastructure Planning Blog 50: An offshore wind DCO, safeguarding transmission and the King’s Speech

Infrastructure Planning Blog 49: Sundowner and BNG on the up

Infrastructure Planning Blog 48: Legal challenge ruled totally without merit, pollution control regimes and football stadiums

Infrastructure Planning Blog 47: Overhead line changes, and enabling data centres

Infrastructure Planning Blog 46: BNG for NSIPs defined but delayed and other news

Infrastructure Planning Blog 45: Largest solar DCO granted and other news

Impact of flexible working on towns and cities - the market and legal considerations
1 September – all change (again) for the Community Infrastructure Levy

TLT adds 29 lawyers creating one of the largest practices of its kind in the UK

TLT hires transport and renewable energy specialist supporting the expansion of its planning team
TLT Partner Appointed Chair of North West Fraud Forum | TLT

TLT Shortlisted for Firm of the Year at Scottish Legal Awards | TLT

TLT Wins Law Firm of the Year at Manchester Legal Awards | TLT

TLT Recognised for Two Awards at The Lawyer Awards 2022 | TLT

TLT Shortlisted for Two Manchester Legal Awards 2022 | TLT

TLT advises Network Homes on £140m sale to Grainger

TLT advises One Housing Group on major affordable housing project

TLT appointed to sports and arts legal services panel

TLT supports Network Homes with affordable housing acquisition

TLT advises Blackfinch on acquisition of two wind energy sites

TLT supports Low Carbon develop UK's largest community-owned solar park

TLT wins expanded role on North West Legal Consortium panel
TLT advises Guinness Asset Management on sale of clean technology assets

TLT advises Alpha Real Renewables on clean energy asset acquisition

BNG - TLT and Belmont Estate talk nature positivity



%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi%20MANCHESTER5.jpg)
%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.avif)




%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi.avif)



%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.avif)








