TLT website banner

Contracts Matter

September 2026

TLT website banner

Welcome to the autumn edition of our contract law update series. In this update, we provide a round-up of some of the most significant contract law cases since our June update to help our clients stay up to date when drafting and negotiating contracts.

Date published

Tuesday 22 September 2026

CONTRACT INTERPRETATION

"Banking Days" across time zones: Place of performance determines the deadline

Songa Product and Chemical Tankers IV AS v Gardsea Shipping Inc [2026]

contract interpretation

High Court rejects buyer's attempt to walk away from minimum quantity obligations

Socar Trading SA v City Trade and Investment SA[2026]

EXCLUSION CLAUSES

Limitation clause held reasonable despite market dominance

Trinsic Collagen Ltd v Procoll Ltd [2026]

LOSS OF BARGAIN

Supreme Court confirms sellers must compensate for loss of bargain despite absence of repudiatory breach

Great Asia Maritime Limited v Orion Shipping and Trading LLC [2026]

PENALTIES

Default interest survives second penalty challenge

Houssein v London Credit Ltd [2026]

GOOD FAITH

Implied terms of good faith and relational contracts: back to basics

Svella Connect Ltd v Virgin Media Ltd [2026]

TERMINATION

Post-termination reserves: Why precise survival drafting matters

QuidPay Finance Ltd v SettleGo Solutions Ltd (t/a OpenPayd) [2026]

Contract interpretation

"Banking Days" across time zones: Place of performance determines the deadline

Songa Product and Chemical Tankers IV AS v Gardsea Shipping Inc [2026]

The High Court held that a contractual payment deadline is determined by the local time in the place of performance, rather than by the latest possible time across all countries referenced in a contractual definition of "Banking Days".

Facts

The parties entered into a contract for the sale of a vessel MT Songa Coral for USD 25 million. Under the agreement, Gardsea Shipping Inc (Buyers) were required to release payment from an escrow account to Songa Product and Chemical Tankers IV AS (Sellers) in Norway no later than three "Banking Days" after notice of readiness (NOR) had been given. The NOR was served on the 2 September 2022 and the parties agreed the third banking day was 8 September 2022, after accounting for weekends and public holidays. The contract defined "Banking Days" by reference to days on which banks were open in multiple jurisdictions.

When payment had not been released by midnight in Norway, the Sellers served notice to cancel the contract. The arbitration tribunal in London concluded that the cancellation notice had been served prematurely. The tribunal held that the Buyers had until midnight in the most westerly time zone in the Banking Days definition (Hawaii) to make payment. The tribunal accepted that this construction had little commercial logic but considered that the contract drafting displaced the usual common law presumption that an obligation to be performed in a particular place must be performed by midnight in that place.

Decision

On appeal, the High Court concluded that the tribunal decision was incorrect in law. The contract required the balance of the purchase price to be released from escrow in Norway on 8 September 2022, and the Buyers were in default as that had not occurred by midnight in Norway.

The court confirmed that whether an obligation has been performed on a particular day is generally determined by reference to local time in the place where the obligation is to be performed. While this presumption is not a strict rule of law, clear contractual wording would be required to rebut it.

Applying the local time presumption, parties need to work forward, ascertaining each calendar day and establishing whether it is a "Banking Day". Determining whether a particular day qualifies as a "Banking Day" may require consideration of bank opening days in several locations, but it does not require parties to assess when each relevant day begins or ends across different time zones. The court considered that this approach reflects reasonable and ordinary commercial understanding and provides a practical and predictable basis for determining deadlines.

Key takeaways
  • Commercial parties should assume that contracts will be interpreted in a way that generally gives an ordinary meaning to words, especially when the ordinary meaning is one that makes complexity manageable.
  • Contracts defining "Banking Days" by reference to multiple countries with different time zones should carefully consider whether the place of performance is sufficiently clear.
  • The court reaffirmed that unless the contract expressly provides otherwise, contractual obligations must be performed by midnight local time at the place of performance.

Contract interpretation

High Court rejects buyer's attempt to walk away from minimum quantity obligations

Socar Trading SA v City Trade and Investment SA [2026]

The High Court held that a buyer of ultra-low sulphur diesel was in repudiatory breach of two sale contracts after taking delivery of only a fraction of the agreed quantities. The court rejected the buyer's arguments that a +/- 10% quantity option and a rollover provision entitled it to walk away from unlifted volumes, finding that the contractual language was clear and unambiguous and that commercial common sense could not be invoked retrospectively to rewrite a bad bargain.

Facts

Socar Trading SA (Seller) and City Trade and Investment SA (Buyer) entered into two contracts for the sale of ultra-low sulphur diesel stored at terminals in Mersin and Samsun, Turkey. Under the Mersin contract, the Buyer agreed to purchase a test parcel of 15,000 metric tonnes (plus or minus 10% at the Buyer's option), and under the Samsun contract, 10,000 metric tonnes on similar terms. The contracts were intended as trial deliveries, with the possibility of extension to a longer-term arrangement.

The pricing under both contracts combined a variable element linked to a published market index with a fixed premium. A special rollover provision required the Buyer to take the full agreed quantity and stipulated that any shortfall would carry over to the following month, with the Buyer bearing additional costs such as storage, insurance and financing.

The Buyer took delivery of only a fraction of the contracted quantities before declaring the contracts to be overpriced and ceasing further performance. The Seller issued notices of default and ultimately terminated both contracts, claiming approximately US$3 million in market loss damages.

Decision

The High Court held that the Buyer was in repudiatory breach of both contracts. The contractual language specifying the quantities and delivery periods was clear and unambiguous. The Buyer's option to vary quantities by 10% was intended to regulate the range of quantities the Buyer could take; it did not relieve the Buyer of the obligation to take at least the minimum amount. Although the rollover provision was intended to operate for the Buyer's benefit (affording it additional time to take delivery), the wording supported the Seller's case that the Buyer had a basic contractual commitment to take the "Quantity" as specified.

The court also declined to imply a term limiting the Buyer's obligations to whatever it managed to lift during the delivery period. Applying the test set out in Marks & Spencer Plc v BNP Paribas [2015], the court held that the proposed implied term was neither so obvious that it went without saying nor necessary to give the contracts business efficacy, and that its implication would conflict with the express contractual terms.

The breach was characterised as repudiatory on the basis that the Buyer's obligation to accept the goods was a condition of the contracts, time being of the essence in respect of the delivery obligations in this type of commercial contract.

Key takeaways
  • The fact that the contracts worked out badly for the buyer was not a reason for departing from the natural language used. The court stated:

"Commercial common sense is only relevant to the extent of how matters would or could have been perceived by the parties, or by reasonable people in the position of the parties, as at the date that the relevant Contract was made. It is not considered retrospectively."

  • Minimum quantity obligations in trial or test contracts carry the same legal weight as in any other agreement. Buyers should not assume that the exploratory nature of a commercial relationship diminishes their contractual commitments.
  • Damages for non-acceptance are assessed at the point when the innocent party should reasonably have gone into the market to mitigate, not at the moment of breach. Sellers should be mindful of the need to act promptly once it becomes apparent that the buyer will not perform.

Exclusion clauses

Limitation clause held reasonable despite market dominance

Trinsic Collagen Ltd v Procoll Ltd [2026]

The High Court has confirmed that a negotiated set of limitation provisions can satisfy the reasonableness test under the Unfair Contract Terms Act 1977, even where the seller is the sole worldwide supplier of the goods and the customer has made significant investments in reliance on the contract.

Facts

Procoll Limited (Seller) agreed to supply Trinsic Collagen Limited (Buyer) with "food grade bovine single alpha chain collagen" under an agreement that stipulated certain quality and testing requirements. The Buyer later alleged that the collagen product supplied did not meet these requirements and claimed more than £7 million in damages for profits it alleged would have been earned had compliant collagen been supplied.

The limitation of liability clause contained a general cap on the Seller's liability of 100% of the price paid by the Buyer in the previous 12 months (although the cap did not apply in cases of deliberate default). The agreement also excluded claims for loss of profits, loss of business, loss of contracts, loss of goodwill, and indirect or consequential loss. The statutory implied terms under sections 13 to 15 of the Sale of Goods Act 1979 were also excluded, in view of the express commitments in the contract regarding compliance with the relevant specifications.

Decision

The court found that the Seller had breached several contractual obligations. It failed to supply a replacement batch for a defective order on one occasion and also breached quality-related provisions for multiple other months, where the results of product testing were ambiguous. One container from the defective order was found to have been affected by microbial contamination, while the batches delivered in the other months in question had undergone collagen reformation, in each case rendering the affected product unfit for purpose.

The Buyer attempted to argue that the Seller's "deliberate default" (which included 'blind eye' knowledge of a breach) prevented it from relying on any limitation. The court rejected this argument on the facts of the case. The Buyer also argued that the limitation clauses were unreasonable under UCTA, on the basis that the Seller, as the sole worldwide supplier of the product, had an unfair advantage in terms of bargaining power and that the Buyer had invested heavily in equipment in reliance on the agreement.

Regarding bargaining power, the court disagreed with the Buyer's argument on the basis that although the Seller occupied a unique market position, the Buyer entered negotiations with significant leverage. It had asserted claims worth at least £4.7 million under an earlier agreement, which could have threatened the Seller's viability as a business. There was also evidence that both parties were legally advised and extensively negotiated the contract. Drafts showed the Buyer attempted to remove the loss of profit exclusion, but the Seller ultimately prevailed on this point in the negotiation.

Beyond relative bargaining power, which the court identified as a key factor in assessing reasonableness under UCTA, several additional considerations supported the validity of the exclusion clauses. First, the court noted that, based on the facts of the case, the excluded losses (particularly loss of profits) were evidently within the parties' contemplation when the contract was entered into. Secondly, there was a stark disparity between the parties' respective economic positions in relation to the agreement since the Buyer expected to generate revenues of approximately £3.5 million per month, while paying only around £30,000 per month for the collagen. Thirdly, the court considered that the Seller would have been unable to meet a claim of the scale envisaged by the Buyer and was unlikely to be capable of satisfying a comparable claim for future loss of profits. Taking these factors into account, the court concluded that the limitation clauses were fair and reasonable.

As a result, the Buyer's claim for £7 million in lost profits failed. The court held that the Buyer was only entitled to a contractual late delivery fee of £3,000. As the Seller was owed £30,000 for an unpaid invoice, it successfully set off this amount against the fee, meaning the Buyer ultimately recovered nothing.

Key takeaways
  • Negotiated limitation clauses are more likely to satisfy UCTA reasonableness requirements, particularly where both parties are legally advised.
  • The parties' relative commercial risk and reward is a relevant factor in assessing the reasonableness of liability caps and exclusions.
  • A supplier's market dominance does not, by itself, establish unequal bargaining power.

Loss of bargain

Supreme Court confirms sellers must compensate for loss of bargain despite absence of repudiatory breach

Great Asia Maritime Limited (Respondent) v Orion Shipping and Trading LLC (Appellant) [2026]

The Supreme Court has upheld a buyer's entitlement to US$1.85 million in loss of bargain damages following cancellation of a vessel sale under the Norwegian Saleform 2012, dismissing the seller's appeal on all grounds.

The judgment rejects both the argument that contractual cancellation breaks the chain of causation and the contention that clear words are needed to confer a right to loss of bargain damages.

Facts

Great Asia Maritime Ltd (Buyers) agreed to purchase the vessel MV Lila Lisbon from Orion Shipping and Trading LLC (Sellers) for US$15 million under a Memorandum of Agreement on the Norwegian Saleform 2012.

Clause 5 of the agreement governed delivery of the vessel, requiring the Sellers to give notice if they anticipated being unable to deliver in time, whereupon the Buyers could elect either to terminate the contract or to agree a new delivery date. Clause 14 obliged the Sellers to compensate the Buyers for “their loss and for all expenses” where the failure to be ready was attributable to the Sellers’ proven negligence, whether or not the Buyers cancelled the agreement.

Following the Sellers’ failure to deliver by the extended cancelling date, the Buyers cancelled the contract and claimed damages for loss of bargain, as the vessel’s market value had increased at the date of cancellation. An arbitration tribunal awarded $1.85 million to the Buyers to compensate for the difference between market price and contract price. However, the High Court reversed the tribunal's decision, finding that the Buyers were not entitled to damages for loss of bargain.

As reported in Contracts Matter in January 2026, the Court of Appeal concluded that the buyer of a vessel was entitled to compensation for “loss of bargain” damages when exercising a contractual right of cancellation for the seller’s default, even though no repudiatory breach had occurred. The Sellers appealed to the Supreme Court, advancing two principal arguments:

  • the "causation principle": that where a party terminates under an express contractual right rather than for repudiatory breach, the resulting loss of bargain is caused by the decision to terminate, not by the breach itself; and
  • the "clear words principle": that since loss of bargain damages would not be available at common law in the absence of a repudiatory breach, express language in clause 14 would be required to confer such a right, and no such language was present.
Decision

The Supreme Court unanimously dismissed the appeal, holding that the language of clause 14 supported the conclusion that "loss" encompassed loss of bargain suffered by Buyers following cancellation. The term "loss" was general and unqualified, and loss of bargain was the most obvious head of loss arising from cancellation. Several contextual factors reinforced this interpretation. The corresponding clause for Buyers' defaults (clause 13) had previously been construed as permitting recovery of loss of bargain damages, and it would be anomalous if clause 14 did not produce the same result. This interpretation also aligned with the normal measure of damages for non-delivery under the Sale of Goods Act 1979 and accorded with established judicial and market understanding of clause 14.

The Supreme Court emphasised that, in the interests of certainty and predictability, where a clause of a standard form contract has an established meaning, that meaning should be upheld unless it is clearly wrong. The court further observed that the commercial consequences of the rival interpretations favoured the Buyers' construction: permitting Sellers to benefit from their own negligence by retaining a vessel that had increased in value would be an uncommercial outcome.

Turning to the Sellers' two arguments, the Supreme Court rejected both. On the causation principle, the Sellers relied on the Court of Appeal's decision in Financings Ltd v Baldock [1963] for the proposition that loss of bargain damages are irrecoverable where a party terminates under an express contractual right rather than for repudiatory breach. Without ruling on the correctness of Financings, the court held that it did not assist the Sellers. Unlike the position in Financings, clause 14 contained a valid express compensation clause specifying what buyers could recover for breach, and there was no reason to construe such a clause as excluding loss of bargain damages in the absence of words to that effect.

On the clear words principle, the Sellers submitted that express language was required to create a right to damages that would not arise at common law, relying on Novasen SA v Alimenta SA [2013]. The Supreme Court rejected this argument, holding that the well-established principle requiring clear words to exclude a party’s common law rights is materially different from a situation where a contract confers additional rights or remedies. There was accordingly no justification for requiring clear words in clause 14 to enable recovery of loss of bargain damages. Novasen was distinguishable as it concerned a right to compensation where the claiming party had suffered no loss at all; clear words would be necessary in such circumstances, but not where, as here, the Buyers had in fact suffered a loss of bargain.

Key takeaways
  • Unqualified references to "loss" will be read broadly. Drafters who intend to limit recovery to specific heads of loss (such as wasted expenditure or losses accrued to the date of termination) must use express language.
  • The Supreme Court placed weight on the fact that the equivalent clause for Buyers' defaults had already been construed as permitting loss of bargain damages. When drafting reciprocal default provisions, parties should ensure that any intended asymmetry in remedies is made clear.
  • The court rejected the argument that exercising a contractual right to cancel breaks the chain of causation for loss of bargain. Sellers (or other defaulting parties) should not assume that granting the innocent party an express termination right will cap their exposure to direct losses only.
  • In the interests of certainty, an established meaning of a standard form clause will be upheld unless clearly wrong. Parties who wish to depart from the market's settled understanding of a standard form provision should use clear and specific drafting to do so.

Penalties

Default interest survives second penalty challenge

Houssein v London Credit Ltd [2026]

The Court of Appeal has considered the case of Houssein v London Credit Ltd for a second time and unanimously dismissed the borrowers' appeal, confirming that a default interest rate of 4% per month was enforceable and did not fall foul of the penalty doctrine.

Facts

London Credit Ltd (LC) agreed to loan £1,881,000 to the third appellant, CEK Investments Limited (CEK), for a period of 12 months. The loan was secured by a debenture over CEK’s assets, personal guarantees from CEK’s directors and third-party mortgages over their family home and several buy-to-let properties. Following drawdown of the loan, LC alleged that a non-occupation covenant had been breached and demanded repayment of the full loan amount, plus default interest.

The main issue revolved around the default interest rate clause in the facility agreement, and whether it constituted a penalty which would render the default interest provision unenforceable. On the first occasion in the High Court, the judge concluded that the default interest did not protect any legitimate interest of LC and was therefore a penalty. The Court of Appeal reversed this finding, holding that the judge had misapplied the Cavendish test and remitted the penalty issue for fresh determination (see our previous insight).

In a lengthy decision in October 2025, the High Court found that the default interest rate of 4% per month was not a penalty and gave guidance on the application of Cavendish Square Holdings BV v Makdessi [2016] in the context of a default rate which could be imposed in response to various defaults under a loan agreement (see Contracts Matter - January 2026). CEK appealed and the case came before the Court of Appeal for a second time.

Decision

The Court of Appeal unanimously dismissed the appeal, upholding the trial judge's conclusion that the default rate of 4% per month was not a penalty. Applying the test in Cavendish Square Holdings BV v Makdessi [2016], the trial judge had identified LC's legitimate interests - in particular, what he termed the "Credit Risk Interest"- and assessed whether the default rate was "out of all proportion" to each such interest. In the circumstances, it was not extortionate for LC to attach an above-market default rate to protect its credit risk. The Court of Appeal held that this was a rationally supportable evaluative judgment and that the borrowers had failed to identify any flaw in the judge's reasoning.

The Court of Appeal also addressed what is required to stop interest running. A valid tender requires the sum to have been set aside and kept available to the payee; a mere offer to repay does not suffice. The borrowers relied on several offers of repayment funded by refinancing from new lenders, arguing that the lender's refusal of those offers barred it from continuing to recover interest. The Court of Appeal rejected that argument, upholding the trial judge's findings.

Key takeaways
  • The Court of Appeal stated: "The question is not whether the legitimate interest is "adequately" protected. That would be to resurrect the now discarded "pre-estimate of loss" test. Rather the question is whether the Default Rate is "out of all proportion" to the legitimate interest in common."
  • A sum of money which becomes payable on breach of a number of different primary obligations (some of which may be more serious than others) is more "susceptible" to being characterised as a penalty than a sum which becomes payable on breach of a single primary obligation.
  • When drafting default interest provisions, it is therefore important that each separate default must reflect a need to protect a legitimate business interest, otherwise the entirety of the provision may fail.

Good faith

Implied terms of good faith and relational contracts: Back to basics

Svella Connect Ltd v Virgin Media Ltd [2026]

In this case, the High Court undertook an extensive review of the law on implied duties of good faith and the concept of "relational contracts". The decision confirms that the courts will apply the ordinary principles governing implied terms, beginning with a careful examination of the parties’ express bargain. Labelling a contract as relational is not a shortcut to an implied duty of good faith.

Facts

Virgin Media engages a series of contractors under framework agreements to expand its fibre optic network throughout the UK. Following a breakdown in relations with one such contractor, Svella Connect Ltd, the parties entered into an Exit & Settlement Agreement dated 24 July 2024, under which Svella waived certain claims while Virgin Media agreed to award further work. Shortly afterwards, Virgin Media's customer nexfibre scaled back its plans, materially reducing the volume of work available to Svella.

Svella brought various claims, most of which were conceded in response to Virgin Media's summary judgment application. The remaining question was whether terms of good faith could be implied into the framework agreements and the Exit & Settlement Agreement, and whether Virgin Media had breached any such terms.

Decision

The judgment provides a thorough review of the current state of the law on implied terms of good faith. Despite "something of an avalanche" of parties trying to show that the contract into which they are seeking to imply a term of good faith is a relational contract, relatively few have succeeded. The judge observed that the label "relational" is best used to describe the quality of the agreed relationship, but it should not be seen as determinative of the argument as to implication of terms.

The High Court held that the correct starting point is to examine the parties’ express bargain and apply the conventional Marks & Spencer principles to determine whether any pleaded implied term of good faith is made out. Central to that analysis is the true nature of the contract and the degree to which the parties have already regulated their relationship. A term cannot of course be implied in respect of a matter which is already covered in the agreement.

The list of characteristics of a relational contract set out in the case of Bates v. Post Office (No. 3) [2019] may assist as a sense-check in the case of long-term collaborative agreements, but they are not an alternative to the proper application of the orthodox rules for the implication of a term in fact. As to whether good faith should be implied in fact or in law, the court noted the “general drift” since Yam Seng in favour of implication in fact, but necessity must remain at the heart of the approach on either basis.

The court concluded that the framework agreements (detailed NEC-based contracts containing a bespoke obligation to act in "a spirit of mutual trust and co-operation") were not relational contracts, and the Bates sense-check confirmed no basis for implying the pleaded terms. The implied terms were even less tenable in respect of the Exit & Settlement Agreement: it is inherently unlikely that duties of good faith should be implied into a carefully negotiated settlement agreement, particularly where the parties had already agreed express reasonable endeavours obligations

Key takeaways
  • Courts will not imply a duty of good faith simply because a contract can be described as relational. The correct approach remains to analyse the parties’ express bargain and consider whether on conventional Marks & Spencer principles any pleaded implied term of good faith is made out.
  • Where the parties have expressly covered a particular aspect of their relationship - for example through reasonable endeavours obligations or bespoke cooperation clauses - there is no gap for an implied term of good faith to fill.
  • Courts are unlikely to imply duties of good faith into a negotiated exit or settlement agreement designed to bring a difficult relationship to an end.

Termination

Post-termination reserves: Why precise survival drafting matters

Quidpay Finance Ltd v Settlego Solutions Ltd (t/a OpenPayd) [2026]

The High Court held that an e-money issuer's reserve clause did not survive termination of its standard terms. Once the agreements ended, it had to repay the reserved funds immediately, notwithstanding a live EUR 9m fraud claim. The decision underscores the importance of considering which provisions should survive termination.

Facts

SettleGo Solutions Limited (trading as "OpenPayd") provided QuidPay Finance Limited (QuidPay) with electronic money and payment services through electronic money accounts in QuidPay's name, with QuidPay in turn providing similar services to its own end-customers. In March 2026, OpenPayd identified suspected authorised push payment fraud totalling nearly EUR 9 million, linked to a Croatian shipyard whose funds had been routed through accounts assigned by QuidPay to two corporate customers and subsequently converted into cryptocurrency.

OpenPayd responded by progressively restricting QuidPay's accounts - initially requiring manual approval for outgoing payments, and later suspending all account activity entirely, including routine transactions such as payroll. OpenPayd then issued a formal notice under its General Terms of Use requiring QuidPay to set aside a reserve of approximately EUR 2.45 million and GBP 7 million, which OpenPayd deducted from QuidPay's accounts.

QuidPay treated these actions as a repudiation of the contract, with the agreements coming to an end in late May 2026. QuidPay brought proceedings seeking the return of the reserved funds. After an initial application for injunctive relief and the resolution of a procedural dispute concerning an alleged legal barrier to releasing the funds, the matter proceeded to a trial of a single preliminary issue: whether the contractual reserve mechanism continued to operate after the agreements had been terminated.

Decision

Ruling in QuidPay's favour, the High Court found that the requirement to hold a reserve was a primary, ongoing obligation that only had effect during the life of the contract. It was not an accrued right capable of persisting beyond termination. Significantly, the termination provisions of the agreement expressly identified which clauses would endure after the relationship ended, and the reserve clause was not among them. The judge observed that it would be hard to justify treating such an obligation as impliedly surviving termination when the contract did not say so. The reserve mechanism therefore fell away on termination, and OpenPayd was obliged to return the funds to QuidPay.

The court also dismissed OpenPayd's reliance on its own post-contractual conduct as a guide to the meaning of the agreement, characterising that approach as 'arguing backwards'. Just because OpenPayd treated the deducted funds in a particular way did not mean that was the correct interpretation of the agreement. The judge also noted that OpenPayd's interpretation of the contract did not fit well with the safeguarding protections afforded to customer funds under the Electronic Money Regulations 2011.

Neither side's arguments based on commercial reasonableness were found to be more persuasive than the other, and the judge concluded that the plain wording of the contract should prevail. OpenPayd was ordered to return the reserve immediately.

Key takeaways
  • Survival clauses should be drafted with precision. Where a contract contains an express list of provisions that endure beyond termination, obligations not included on that list are unlikely to be treated as impliedly surviving. Parties wishing to preserve particular rights post-termination must ensure those rights are clearly captured in the relevant survival provision.
  • In this case, the reserve provisions in the Acquiring Service Terms were not expressly listed as applying post-termination in the survival clause of the General Terms. It is worth reviewing and updating general terms to make it clear that any reserve provisions in related contracts apply expressly post-termination.
  • Post-contractual conduct cannot rewrite the bargain. A party's unilateral behaviour after a contract has been entered into will not be accepted as evidence of what the agreement was intended to mean. Courts will focus on the language agreed at the time the contract was made.

Contributors: Angad Singh, Priya Kaur

This publication is intended for general guidance and represents our understanding of the relevant law and practice as at September 2026. Specific advice should be sought for specific cases. For more information see our terms & conditions.

Abstract overlapping curved shapes in varying shades of violet and purple on a solid violet background.

Legal insights & events

Keep up to date on the issues that matter.

Abstract yellow background with overlapping translucent olive green curved shapes.

Follow us

Find us on social media