What is the key to speeding up planning appeal inquiries?
Last month, the Government published the report of the Independent Review of Planning Appeal Inquiries. This sets out 22 recommendations for change. These range from simple improvements in timetabling to an increased use of technology.
The recommendations can be grouped into three main areas:
Earlier engagement by all parties, including:
- Ensuring that only complete appeals can be submitted and a start letter is issued within 5 working days of the receipt of each inquiry appeal. The start letter should include the name of the inspector who will conduct the appeal;
- Case management engagement between the inspector and the parties not later than 7 weeks after the start letter;
- Following the case management engagement, the inspector should issue clear directions to the parties about the final stages of preparation and how evidence will be examined no later than 8 weeks after the start letter;
- The inspector telling the parties, at the pre-inquiry stage, how evidence will be examined at the inquiry.
Greater certainty about timescales, including:
- The Planning Inspectorate to lead on identifying a date for the inquiry, and all inquiries starting within 13 to 16 weeks of the start letter;
- 90% of cases decided by the Inspector should go from receipt to decision within 24 weeks, with the remaining 10% of cases being dealt with within 26 weeks;
- All cases decided by the Secretary of State should proceed from receipt to submission of the inspector's report within 30 weeks;
- To encourage a timely submission of documents, the Planning Inspectorate should impose sanctions where a party has acted unreasonably and caused another party to incur unnecessary or wasted costs.
Harnessing technology to improve efficiency and transparency, including:
- The introduction of a new online Planning Appeal portal for the submission of inquiry appeals. This will be introduced by December 2019, with pilot testing to start in May 2019;
- All documents for an appeal should be published on the new portal at the earliest opportunity following their submission
- Further uses for technology should be identified to improve the efficiency and transparency of the process.
Will the average time to decide a planning appeal be "slashed from 47 to 26 weeks", as the Government claims? Katherine Evans, Head of Planning comments that " speeding up the time that it takes for appeals to be validated and the allocation of an Inspector are areas of particular concern but this does not only affect appeals heard at inquiry. It is a pity that these improvements aren't being aimed at all types of appeal. Recruitment of additional Inspectors by the Planning Inspectorate must also be a priority."
Contributor: Alexandra Holsgrove Jones
This publication is intended for general guidance and represents our understanding of the relevant law and practice as at March 2019. Specific advice should be sought for specific cases. For more information see our terms & conditions.
Get in touch
Get in touch
Insights & events

Infrastructure Planning Blog 45: Largest solar DCO granted and other news

Infrastructure Planning Blog 44: Plans, purdah and publication

Infrastructure Planning Blog 43: Slow, slow, quick, no go for infrastructure planning

Infrastructure Planning Blog 42: Nuclear reforms, discharge of requirements and NPPF changes

Infrastructure Planning Blog 41: New Welsh guidance, the use of AI in planning and other updates

Northern Ireland Planning and Environment update: Minerals

Infrastructure Planning Blog 40: A conference and another revocation

Infrastructure consent order regime in Wales: Updates

Infrastructure Planning Blog 39: Fenwick Solar Farm, Sizewell C and EIA case law

Infrastructure Planning Blog 38: A new wind DCO, and European streamlining

Infrastructure Planning Blog 37: Fission 'n' chippy

Infrastructure Planning Blog 36: Application Fees, the Holocaust Memorial, data centres and correction orders

Infrastructure Planning Blog 35: Water, electricity markets, delays

Infrastructure Planning Blog 34: Data centres can be NSIPs after a record DCO year

Planning and Infrastructure Act 2025: What developers need to know

Impact of flexible working on towns and cities - the market and legal considerations
1 September – all change (again) for the Community Infrastructure Levy

TLT adds 29 lawyers creating one of the largest practices of its kind in the UK

TLT hires transport and renewable energy specialist supporting the expansion of its planning team
TLT Partner Appointed Chair of North West Fraud Forum | TLT

TLT Shortlisted for Firm of the Year at Scottish Legal Awards | TLT

TLT Wins Law Firm of the Year at Manchester Legal Awards | TLT

TLT Recognised for Two Awards at The Lawyer Awards 2022 | TLT

TLT Shortlisted for Two Manchester Legal Awards 2022 | TLT

TLT advises Network Homes on £140m sale to Grainger

TLT advises One Housing Group on major affordable housing project

TLT appointed to sports and arts legal services panel

TLT supports Network Homes with affordable housing acquisition

TLT advises Blackfinch on acquisition of two wind energy sites

TLT supports Low Carbon develop UK's largest community-owned solar park

TLT wins expanded role on North West Legal Consortium panel
TLT advises Guinness Asset Management on sale of clean technology assets

TLT advises Alpha Real Renewables on clean energy asset acquisition

Biodiversity Net Gain: What’s changing and what it means for you

BNG - TLT and Belmont Estate talk nature positivity




%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.avif)




%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi.avif)



%20%C3%94%C3%87%C3%B4%20790px%20X%20451px%2072ppi2.avif)